THE LEGAL QUESTION
Was the subcontractor liable for the flood and was the settlement sum within the range of reasonable settlements recoverable as damages?
The facts
A sprinkler tank overflowed after a valve connection failed, damaging electrical equipment. Claims travelled through the construction subcontract chain. Siemens settled the claims against it and maintained its Part 20 claim against Supershield. The trial judge found relevant installation obligations and a reasonable settlement.
What the court decided
The Court of Appeal dismissed the appeal. For settlement reasonableness, the question was whether the settlement fell within the range of what was reasonable, rather than the appellate judge’s own hypothetical valuation of the settled litigation.
Why: the reasoning
The court examined the contract and breach before reaching damages. It assessed settlement against the prospects and risks of the claims as a whole. Its treatment of causation and remoteness did not dispense with the duty, breach or causal link required for recovery.
Why it matters and its limits
Helps explain why a reasoned challenge to the settlement evidence matters, while a different preferred negotiating figure is not necessarily decisive.
WHAT IT DOES NOT DECIDE
Not authority that every motor insurer settlement binds a policyholder or uninsured driver.
Not a reason to skip proof of the actual statutory, contractual or assigned cause of action.
Reasonableness and causation remain specific to the facts and duty.
Status and authority
PROCEDURAL STAGE
Appeal from a Technology and Construction Court judgment on contractual liability and recovery of a third-party settlement.
APPEAL STATUS · NOT CONFIRMED
The dismissal of this appeal is verified. Further appeal outcome was not established by the bounded official searches and is unconfirmed.
LATER TREATMENT
John Grimes Partnership v Gubbins [2013] EWCA Civ 37 [21]–[24] treats Supershield as binding Court of Appeal analysis of contractual remoteness. That later decision is not a later holding that any motor settlement is recoverable.
BINDING EFFECT
Court of Appeal authority for lower courts in England and Wales on the contractual issues decided; persuasive outside that jurisdiction, subject to later appellate law.
Guides that use this decision
The judgment
This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.
Sources
The numbers match the sources of the guide this summary was researched for.
[24] Supershield Ltd v Siemens Building Technologies FE Ltd · [28]–[29], [45]–[48]
The issue which the judge has to decide is not what assessment he would have made of the likely outcome of the settled litigation, but whether the settlement was within the range of what was reasonable.
About this sourceOfficial text[27] John Grimes Partnership Ltd v Gubbins · [21]–[24]
it is unnecessary to take time on a detailed analysis of the other speeches, since the decision has been carefully considered by this court in a decision binding upon us, Supershield Ltd.-v-Siemens Building Technologies FE Ltd. (ante).
About this sourceOfficial text[68] Supershield Ltd v Siemens Building Technologies FE Ltd · [2], [3], [4], [46]
The judge found that the probable cause of failure of the nut and bolt connection between the lever arm and the ball valve was a lack of sufficient tightening when the ball valve was installed and that, under the Supershield subcontract, Supershield had an obligation both to install the ball valve and lever arm and to carry out any adjustments which were necessary to ensure that the ball valve was operating correctly. Those findings were sufficient for the purposes of establishing liability between Supershield and Siemens, but he also found on the balance of probability that Supershield had in fact installed the ball valve.
On the issue of damages, Supershield disputed Siemens’ claim that the sum for which Siemens had settled the claims made against it reasonably reflected the strength of the defences available to it. The judge found that overall the settlement was reasonable. He therefore gave judgment for Siemens on its part 20 claim against Supershield for the amount of the settlement (£2,864,080.00) and interest.
Supershield appeals against the judgment on three grounds. These are : 1. The judge misconstrued the subcontract. On its proper construction, the subcontract works did not include the installation of the ball valve. 2. The judge was wrong to find as a fact that Supershield installed the ball valve. 3. The judge was wrong to find that the figure for which Siemens agreed to settle the claims against it was reasonable.
I would dismiss the appeal.
About this sourceOfficial text[70] John Grimes Partnership Ltd v Gubbins · [1], [9], [31], [34]
This appeal raises an issue of some importance about the law on the remoteness of damage in cases of breach of contract. Can a developer of land, whose development scheme is delayed in its implementation by the failure of a consulting engineer to perform tasks which he has contracted to perform by an agreed date, recover damages for the loss he suffers thereby from a diminution in the market value of the development which occurs during the period for which its completion is delayed?
The agreed evidence of the valuers for each side gave a figure for the gross sales value of the development as at that date of £3,827,500, had it been completed by then. There was also evidence that by July 2009, that figure had fallen by £398,000 to £3,429,500, prices having fallen by about 14% during that period of just over one year. But the Judge took the view that any loss associated with the decline in market values, if recoverable at all, would need to be assessed. He therefore dealt with the position at law as a matter of principle.
Some markets are extremely volatile by nature. Furthermore, circumstances at the time of contracting may be such as to render it foreseeable that extreme volatility could be experienced in certain foreseeable circumstances within the lifetime of the contract. Accordingly, I wonder in retrospect whether I was correct in paragraph 88 of my judgment in Pindell to attribute to Lord Rodger, Lord Walker and Baroness Hale in The Achilleas, above, the view that the consequences of extremely volatile market conditions are, axiomatically, irrecoverable. Happily this issue does not arise for decision here, as indeed it did not arise for decision in Pindell. When it does, I doubt if it permits of so trenchant or simplistic an answer as I was then, perhaps incautiously, inclined to supply.
I conclude, therefore, that the Judge was right to find that there was nothing to take this case out of the conventional approach to remoteness of damage in contract cases. It follows that I would dismiss this appeal.
About this sourceOfficial text
General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.