Supershield Ltd v Siemens Building Technologies FE Ltd
PUBLISHED BY · The National ArchivesNATIONS · England and WalesCHECKED · 5 November 2026
This judgment is cited in one guide on this site. Below you will find the official text, the version we read, the guides that cite it and the exact passages they quote.
OUR SUMMARY · COURT DECISION
Supershield Ltd v Siemens Building Technologies FE Ltd
[2010] EWCA Civ 7 · Court of Appeal (Civil Division) · 20 January 2010
Was the subcontractor liable for the flood and was the settlement sum within the range of reasonable settlements recoverable as damages?
OFFICIAL TEXT · PRIMARY SOURCE
Read the official version
The full judgment is published at the source below. Our pages explain it in general terms and do not replace it.
VERSION AND DATES
The version the guides were researched from.
| Version | Status | Source |
|---|---|---|
| 20 January 2010[2010] EWCA Civ 7 | —PUBLISHED 20 JANUARY 2010 | caselaw.nationalarchives.gov.uk |
GUIDES THAT CITE IT
QUOTED PASSAGES
Passages quoted in the guides 5 PASSAGES
The exact words the guides rely on, with where each passage sits in the document and the version it comes from.
[2] · version of 20 January 2010
The judge found that the probable cause of failure of the nut and bolt connection between the lever arm and the ball valve was a lack of sufficient tightening when the ball valve was installed and that, under the Supershield subcontract, Supershield had an obligation both to install the ball valve and lever arm and to carry out any adjustments which were necessary to ensure that the ball valve was operating correctly. Those findings were sufficient for the purposes of establishing liability between Supershield and Siemens, but he also found on the balance of probability that Supershield had in fact installed the ball valve.
[3] · version of 20 January 2010
On the issue of damages, Supershield disputed Siemens’ claim that the sum for which Siemens had settled the claims made against it reasonably reflected the strength of the defences available to it. The judge found that overall the settlement was reasonable. He therefore gave judgment for Siemens on its part 20 claim against Supershield for the amount of the settlement (£2,864,080.00) and interest.
[4] · version of 20 January 2010
Supershield appeals against the judgment on three grounds. These are : 1. The judge misconstrued the subcontract. On its proper construction, the subcontract works did not include the installation of the ball valve. 2. The judge was wrong to find as a fact that Supershield installed the ball valve. 3. The judge was wrong to find that the figure for which Siemens agreed to settle the claims against it was reasonable.
[28] · version of 20 January 2010
The issue which the judge has to decide is not what assessment he would have made of the likely outcome of the settled litigation, but whether the settlement was within the range of what was reasonable.
[46] · version of 20 January 2010
I would dismiss the appeal.
General information, not legal advice. Always check the official text.