John Grimes Partnership Ltd v Gubbins
PUBLISHED BY · The National ArchivesNATIONS · England and WalesCHECKED · 5 November 2026
This judgment is cited in one guide on this site. Below you will find the official text, the version we read, the guides that cite it and the exact passages they quote.
OUR SUMMARY · COURT DECISION
John Grimes Partnership Ltd v Gubbins
[2013] EWCA Civ 37 · Court of Appeal (Civil Division) · 5 February 2013
Could losses from a fall in the property market be recoverable after an engineer’s delay, applying the contractual remoteness approach discussed in Supershield?
OFFICIAL TEXT · PRIMARY SOURCE
Read the official version
The full judgment is published at the source below. Our pages explain it in general terms and do not replace it.
VERSION AND DATES
The version the guides were researched from.
| Version | Status | Source |
|---|---|---|
| 5 February 2013[2013] EWCA Civ 37 | —PUBLISHED 5 FEBRUARY 2013 | caselaw.nationalarchives.gov.uk |
GUIDES THAT CITE IT
QUOTED PASSAGES
Passages quoted in the guides 5 PASSAGES
The exact words the guides rely on, with where each passage sits in the document and the version it comes from.
[1] · version of 5 February 2013
This appeal raises an issue of some importance about the law on the remoteness of damage in cases of breach of contract. Can a developer of land, whose development scheme is delayed in its implementation by the failure of a consulting engineer to perform tasks which he has contracted to perform by an agreed date, recover damages for the loss he suffers thereby from a diminution in the market value of the development which occurs during the period for which its completion is delayed?
[9] · version of 5 February 2013
The agreed evidence of the valuers for each side gave a figure for the gross sales value of the development as at that date of £3,827,500, had it been completed by then. There was also evidence that by July 2009, that figure had fallen by £398,000 to £3,429,500, prices having fallen by about 14% during that period of just over one year. But the Judge took the view that any loss associated with the decline in market values, if recoverable at all, would need to be assessed. He therefore dealt with the position at law as a matter of principle.
[21] · version of 5 February 2013
it is unnecessary to take time on a detailed analysis of the other speeches, since the decision has been carefully considered by this court in a decision binding upon us, Supershield Ltd.-v-Siemens Building Technologies FE Ltd. (ante).
[31] · version of 5 February 2013
I conclude, therefore, that the Judge was right to find that there was nothing to take this case out of the conventional approach to remoteness of damage in contract cases. It follows that I would dismiss this appeal.
[34] · version of 5 February 2013
Some markets are extremely volatile by nature. Furthermore, circumstances at the time of contracting may be such as to render it foreseeable that extreme volatility could be experienced in certain foreseeable circumstances within the lifetime of the contract. Accordingly, I wonder in retrospect whether I was correct in paragraph 88 of my judgment in Pindell to attribute to Lord Rodger, Lord Walker and Baroness Hale in The Achilleas, above, the view that the consequences of extremely volatile market conditions are, axiomatically, irrecoverable. Happily this issue does not arise for decision here, as indeed it did not arise for decision in Pindell. When it does, I doubt if it permits of so trenchant or simplistic an answer as I was then, perhaps incautiously, inclined to supply.