John Grimes Partnership Ltd v Gubbins

CITATION
[2013] EWCA Civ 37
COURT
Court of Appeal (Civil Division)
LEGAL SYSTEM
England and Wales
DATE OF DECISION
5 February 2013
APPEAL STATUS
Not confirmed
PARAGRAPHS RELIED ON
[1]–[12] facts and issue, [13]–[16] arguments, [21]–[24] Supershield and remoteness, [31] express dismissal; [32]–[35] concurrences and volatility qualification

THE LEGAL QUESTION

Could losses from a fall in the property market be recoverable after an engineer’s delay, applying the contractual remoteness approach discussed in Supershield?

The facts

An engineer was retained for road and drainage design and related approvals for a housing development. The developer counterclaimed for loss caused by delay. The appeal addressed the legal recoverability of the type of loss, with assessment of quantum left for later.

What the court decided

The appeal was dismissed. The court applied the ordinary contractual remoteness approach in the circumstances and held that there was no basis for departing from it on the evidence; it did not itself assess a final damages figure.

Why: the reasoning

The court considered the contractual undertaking and the parties’ objective knowledge, treating Supershield as binding Court of Appeal consideration of the relevant remoteness authorities. The decision’s use here is confined to that later treatment, not a motor-insurance settlement rule.

Why it matters and its limits

Provides verified primary later treatment for the limited contractual character of the Supershield analysis.

WHAT IT DOES NOT DECIDE

  • No RTA s. 151 or NI art. 98 recovery holding.

  • An amount illustrated or claimed in the litigation is not a damages award made by this appeal.

  • The case is a supporting authority record; the article’s practical settlement discussion relies directly on Supershield.

Status and authority

PROCEDURAL STAGE

Court of Appeal determination of a contractual damages/remoteness issue arising from an engineer’s fee claim and counterclaim.

APPEAL STATUS · NOT CONFIRMED

The Court of Appeal dismissal is verified; further appeal history is unconfirmed.

LATER TREATMENT

No further appellate outcome established in the bounded official citation/name searches; no assertion of an exhaustive later-treatment search is made.

BINDING EFFECT

Court of Appeal authority in England and Wales on the contractual issue decided; persuasive elsewhere, subject to later appellate law.

Guides that use this decision

An insurer or the MIB wants me to repay money it paid out. What can I do?Guide · Main guide

The judgment

This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.

Sources

The numbers match the sources of the guide this summary was researched for.

  1. [27] John Grimes Partnership Ltd v Gubbins · [21]–[24]

    it is unnecessary to take time on a detailed analysis of the other speeches, since the decision has been carefully considered by this court in a decision binding upon us, Supershield Ltd.-v-Siemens Building Technologies FE Ltd. (ante).
    About this sourceOfficial text
  2. [70] John Grimes Partnership Ltd v Gubbins · [1], [9], [31], [34]

    This appeal raises an issue of some importance about the law on the remoteness of damage in cases of breach of contract. Can a developer of land, whose development scheme is delayed in its implementation by the failure of a consulting engineer to perform tasks which he has contracted to perform by an agreed date, recover damages for the loss he suffers thereby from a diminution in the market value of the development which occurs during the period for which its completion is delayed?
    The agreed evidence of the valuers for each side gave a figure for the gross sales value of the development as at that date of £3,827,500, had it been completed by then. There was also evidence that by July 2009, that figure had fallen by £398,000 to £3,429,500, prices having fallen by about 14% during that period of just over one year. But the Judge took the view that any loss associated with the decline in market values, if recoverable at all, would need to be assessed. He therefore dealt with the position at law as a matter of principle.
    Some markets are extremely volatile by nature. Furthermore, circumstances at the time of contracting may be such as to render it foreseeable that extreme volatility could be experienced in certain foreseeable circumstances within the lifetime of the contract. Accordingly, I wonder in retrospect whether I was correct in paragraph 88 of my judgment in Pindell to attribute to Lord Rodger, Lord Walker and Baroness Hale in The Achilleas, above, the view that the consequences of extremely volatile market conditions are, axiomatically, irrecoverable. Happily this issue does not arise for decision here, as indeed it did not arise for decision in Pindell. When it does, I doubt if it permits of so trenchant or simplistic an answer as I was then, perhaps incautiously, inclined to supply.
    I conclude, therefore, that the Judge was right to find that there was nothing to take this case out of the conventional approach to remoteness of damage in contract cases. It follows that I would dismiss this appeal.
    About this sourceOfficial text

General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.

Install on iPhone or iPad

  1. Tap the Share button in Safari (the square with an upward arrow).
  2. Choose Add to Home Screen.
  3. Tap Add. The app appears next to your other apps.

The first steps after a collision, the checklists and the glossary stay available without signal.