Invitation to Submit Final Tenders for the London Highway Maintenance and Projects Framework: Scope
PUBLISHED BY · Transport for LondonNATIONS · EnglandCHECKED · 6 November 2026
This document is cited in one guide on this site. Below you will find the official text, the version we read, the guides that cite it and the exact passages they quote.
OFFICIAL TEXT · PRIMARY SOURCE
Read the official version
The full document is published at the source below. Check its date before relying on it.
VERSION AND DATES
The version the guides were researched from.
| Version | Status | Source |
|---|---|---|
| UndatedFinal, May 2020; TfL reference tfl_scp_001746a | —PUBLISHED 30 JUNE 2025 | foi.tfl.gov.uk |
GUIDES THAT CITE IT
QUOTED PASSAGES
Passages quoted in the guides 2 PASSAGES
The exact words the guides rely on, with where each passage sits in the document and the version it comes from.
cl. S115.49, printed p. 23
Where the price of the repair is under £10,000 when calculated using the Price List, the Contractor is responsible for the recovery of the costs. Any recovered sums are retained by the Contractor.
cl. S115.50, printed p. 23
Where the price of the repair is over £10,000 when calculated using the Price List, the Contractor provides such evidence and photographs to the Client or the Client’s representative to facilitate the recovery of the costs. The Contractor is reimbursed by the Client in accordance with the contract