Guide · Civil courts, legal help and funding

How does a road accident claim proceed in Northern Ireland?

For a Northern Ireland road-accident claim, you normally exchange a detailed claim letter, a reasoned response and relevant evidence before starting a County Court civil bill or, where appropriate, a High Court writ. [1] [2] [3] [6] [17] Official Injury Claim is not the route for a Northern Ireland accident, and Northern Ireland small claims excludes road traffic accident damages even when the claim is damage-only and low in value. [21] [10] Check limitation early, because the pre-action process does not replace the required court issue step and protective early issue may be needed. [19] [12] [3] [9]

Updated
Sources checked
November 2026
Reading time
16 minutes
Where it applies
Northern Ireland
Category
Civil courts, legal help and funding
Contents 17 sections
  1. Who this guide is for
  2. Choose the Northern Ireland route
  3. Small claims does not cover damage-only crashes
  4. Before a County Court civil bill: send a proper claim
  5. Give the County Court defendant time to investigate
  6. Check the separate High Court pre-action steps
  7. Prepare, issue and serve the County Court papers
  8. Respond, exchange evidence and reach a County Court hearing
  9. How a High Court case moves towards trial
  10. What the Northern Ireland decisions illustrate
  11. Protect limitation and agree how the case is funded
  12. Deadlines
  13. Your checklist
  14. Common questions
  15. Court decisions in this guide
  16. Organisations
  17. Sources

Who this guide is for

Who it is for

  • People making or defending injury or damage-only road traffic claims in Northern Ireland.

Not covered here

  • Republic of Ireland procedure; cross-border forum selection is signposted.

  • England and Wales OIC, track limits, Part 36 and QOCS.

  • Detailed NI funding, costs, default challenge and enforcement.

Dates and the rules in force

Ordinary civil accident claims using Northern Ireland procedure, assessed as at 3 November 2026; the accident/accrual/knowledge and procedural-stage dates must be checked separately.

  • High Court PD 4/2026 has effect from 13 October 2026 and applies to all injury and damage-only King’s Bench actions.

  • County Court protocol remains separate; live rules versions and current fees checked on 3 November 2026.

  • Proposed financial-limit increases do not replace the operative limits until brought into force.

Choose the Northern Ireland route

Applies to: Northern Ireland

If your accident claim belongs in Northern Ireland, use Northern Ireland procedure. Official Injury Claim is for qualifying accidents in England and Wales, so it is not the injury-claim route for a Northern Ireland collision. In Northern Ireland the person bringing the court case is called the plaintiff. [21] [20]

For an ordinary accident damages claim, the County Court’s current general limit is £30,000; claims within £10,000 are generally heard by a district judge, subject to the rules. Higher-value claims normally belong in the High Court. Value is not the only issue: check jurisdiction, the correct defendant, where service will take place and the evidence supporting your valuation before choosing the court. Abandoning an excess to stay within the County Court limit gives up that excess for the cause of action. [11] [12]

The County Court uses a civil bill. The High Court ordinarily uses a writ for accident claims in tort or for damages for personal injury or property damage. Each court has its own pre-action requirements. [12] [17] [1] [6]

If the vehicle or accident has an Irish connection, use the cross-border guide to distinguish the insurer or bureau route, jurisdiction and applicable law before starting a case.

Small claims does not cover damage-only crashes

Applies to: Northern Ireland

You cannot use Northern Ireland small claims for damages arising from a road traffic accident, even if nobody was injured and the repair bill is below £5,000. Order 26 rule 2 of the County Court Rules excludes both personal injury claims and damages in respect of a road traffic accident. A low value does not remove that exclusion. [10] [30]

Example: a disputed £1,200 repair claim caused by a collision follows the ordinary civil-bill route if it belongs in the County Court, after the applicable pre-action steps. It does not become a small claim because it is damage-only. [10] [12] [1]

Before a County Court civil bill: send a proper claim

Applies to: Northern Ireland

The County Court Pre-Action Protocol covers personal injury and damage-only road traffic claims. The court expects both sides to follow it before proceedings. If you have no solicitor, comply as far as reasonably possible; a represented party who knows you are unrepresented should send you a copy. [1]

Once there is enough information for a realistic claim, your solicitor should send a detailed letter of claim to the proposed defendant’s representative. It should explain what happened, why the defendant is responsible, your injuries, provisional financial losses, your address and any hospital attended. Ask for the insurer’s details and send the known insurer a copy. The protocol’s Appendix A provides a model. [2] [31]

For vehicle damage or replacement hire, also give your date of birth, the heads of loss, whether your vehicle is roadworthy or drivable, any relevant occupation and whether you could afford to pay replacement costs yourself. Provide the available repair, recovery, storage and hire documents. If you rely on inability to pay upfront, the protocol calls for relevant financial material, if available, including three months’ bank statements and information about income, debts and outgoings. These are documents about your actual claim, rather than a standard entitlement to every charge. [2] [4]

Give the County Court defendant time to investigate

Applies to: Northern Ireland

If neither the defendant nor their solicitor or insurer replies to the letter of claim within 21 days, paragraph 5.6 says the plaintiff should proceed to issue. However, you may issue sooner where limitation or another reason requires protection. Record when the letter was sent and received; do not confuse this pre-action period with the response time for a served civil bill. [3]

After acknowledgment of the letter, the defendant’s solicitor or insurer has up to 3 months to investigate an injury claim, or 2 months for a damage-only road traffic claim. By the end they should state whether liability is admitted or denied and explain any denial, causation dispute or allegation that you were partly at fault. If the accident happened outside Northern Ireland or the defendant is outside the jurisdiction, the protocol extends the initial 21-day period to 42 days and the investigation period to 6 months for injury or 4 months for damage-only claims. Protective issue remains possible. [3]

If the defendant denies liability or causation, their reply ought to include relevant material documents they hold. If liability and causation are admitted, your solicitor should disclose the special losses, supporting documents and available medical evidence before issue. Under this County Court protocol an admission of liability binds the defendant or insurer, with an exception for subsequent evidence of fraud. [4]

Both sides should consider negotiation or alternative dispute resolution, such as mediation, and may have to show the court that they did so. The protocol says nobody can or should be forced to mediate. The Law Society of Northern Ireland’s mediation referral explains the local option. [5] [24]

Check the separate High Court pre-action steps

Applies to: Northern Ireland

From 13 October 2026, Practice Direction 4 of 2026 applies to all personal injury and damage-only civil actions in the High Court’s King’s Bench Division. It replaces the 2008 High Court direction and protocol. Use its requirements for a High Court case. [6]

The High Court letter should include your full name, address, date of birth and National Insurance number, the accident’s date, time and place, the facts, those said to be responsible, any other proposed defendant, injuries, financial loss and hospital details. Vehicle, hire and storage claims require the available relevant supporting information. Where liability is admitted, send available medical evidence and a detailed schedule of past and future losses with receipts and invoices, updating ongoing loss. [7]

The defendant should acknowledge and identify the insurer within 21 days. The usual investigation maximum is 3 months from acknowledgment; a defendant needing more time must explain before it expires why, what investigation remains and how long it will take. For accidents outside Northern Ireland or defendants outside the jurisdiction, the 21-day and 3-month periods normally extend up to 42 days and 6 months. [8]

Where liability is denied, proceedings should generally wait until after 4 months from acknowledgment. Where liability is admitted, the normal wait is 28 days after service of the medical evidence and loss documents specified in paragraph 4.18. Early issue may be necessary to protect your position, particularly against limitation. A properly agreed standstill may be an option requiring advice on its terms; merely exchanging letters does not itself create one. The parties should consider negotiation or ADR. The court may impose costs or procedural penalties, including a stay, for non-compliance. [9]

Prepare, issue and serve the County Court papers

Applies to: Northern Ireland

Use the current ordinary civil bill, Form 9, with the appropriate Form 10 endorsement, and set out the particulars of your claim, including any interest sought. [34] Check the official court rules and forms against the current rules. A completed form on your desk is not enough: under Order 6 rule 1 a civil bill is deemed issued through specified steps, including receipt by an authorised process server for service, a solicitor’s acceptance of service or posting where postal service is used. Check the service method and keep proof of the relevant dates. [12] [23]

To preserve the relevant motor insurer’s statutory duty to satisfy a qualifying judgment, arrange notice of the proceedings to the insurer. Article 98A makes notice before, or within 7 days after, commencement a condition of the insurer’s statutory duty to satisfy the judgment, subject to its other exceptions. County Court Order 52 Part I rule 1 prescribes Form 292. An earlier accident notification or claim letter should not be assumed to fulfil the separate notice of proceedings requirement. [13] [27]

For fees payable from 1 April 2026 to 31 March 2027, the County Court civil-bill fee is £244 for a claim up to £1,000, £269 over £1,000 up to £5,000, and £302 over £5,000. A certificate of readiness costs £407. These are court fees, separate from your solicitor’s charges, expert costs and any costs payable to another party; check the current fee schedule when lodging papers. [22]

The current County Court guidance requires civil bills and notices of intention to defend to be lodged at the court office in hard copy. The Civil Processing Centre’s service standards offer help with County Court administrative processes, rather than legal advice. Confirm the correct office and lodgement arrangements for your ordinary accident civil bill. [23] [33]

Respond, exchange evidence and reach a County Court hearing

Applies to: Northern Ireland

If you intend to defend a civil bill, serve the other parties with Form 42, the notice of intention to defend, within 21 days from service. At the same time, deliver a copy of both the civil bill and notice to the chief clerk; the current guidance requires hard-copy defence notices at the court office. A late notice needs written consent or the judge’s leave. [23] The rule generally counts from the end of the service day and provides for expiry on a day when the office is closed; check the actual service method and any order. Send papers promptly to the insurer and solicitor handling the defence. For a judgment already entered, use the Northern Ireland challenge and enforcement guide. [14]

In an injury case, the plaintiff must serve medical evidence substantiating the injuries within 14 days after service of the defence notice, subject to the court’s power over procedural time limits. The parties deal with the disputed issues, relevant documents and any necessary expert evidence before trial. Witness evidence is generally oral on oath; disclosed reports and photographs have particular admissibility rules, and a party may require the report’s maker to attend on sufficient notice. [16]

After procedural applications before trial (interlocutory matters) are finished, the plaintiff requests a hearing using Form 43, the certificate of readiness, and serves a copy on the other parties. It cannot normally be lodged until 21 days after the defence notice was served; the plaintiff must give at least 14 days’ written warning of intended lodgement. If no certificate is delivered within 6 months after the defence notice, the clerk lists the case for directions, which may include a stay or dismissal. Issuing a civil bill therefore does not by itself make the case ready for a hearing. [15]

If the dispute reaches a hearing, the judge decides the disputed claim using the evidence. The plaintiff must prove the loss claimed; witnesses, documents and appropriate expert evidence are how the parties put the disputed facts before the court. A claimed hire charge is not established simply by presenting an invoice. [16] [38]

How a High Court case moves towards trial

Applies to: Northern Ireland

The plaintiff issues and arranges service of a writ. A writ is initially valid for service for 12 months from issue, with renewal requiring the court’s order. For a writ served within Northern Ireland, the defendant’s ordinary appearance period is 14 days including the day of service; service outside the jurisdiction uses different periods. A defendant who appears and intends to defend normally serves a defence within 6 weeks after the time limited for appearance or service of the statement of claim, whichever is later, subject to the rules and court orders. Unless the court directs otherwise, the Long Vacation is excluded when calculating time for serving pleadings, including a defence. Order 3 also governs calculation, office closure and extensions, including written-consent extensions for pleadings or other documents. [35] For help dealing with served papers, see receiving court papers after a crash. [17]

Under the current direction, the court lists a first review before the Master 9 months after the memorandum of appearance is filed. The parties complete the first-review questionnaire and the plaintiff ensures the review fee is paid before listing; the review examines readiness for trial. The parties must disclose properly discoverable documents and comply with directions about evidence. A proposed transfer between the High Court and County Court should allow the opponent to consider the evidence; an application should not normally be brought while that opponent says further medical or other expert evidence is awaited. [18]

Order 34 rule 2 requires the plaintiff to set down within 6 weeks after pleadings close, or the period fixed by court order. If the plaintiff fails, the defendant may set down or seek dismissal; the court decides the response. The current direction says no trial date is fixed until the action is set down and fees paid, followed by judicial review within 4 to 6 weeks or earlier on request. These stages require active preparation; a review date is not a promise of a trial or settlement date. [28] [18]

For fees payable from 1 April 2026 to 31 March 2027, the published High Court fees include £326 for sealing a writ and £488 for setting down without a jury. Check the current fee schedule and the entry applicable to your particular action. [32]

What the Northern Ireland decisions illustrate

Applies to: Northern Ireland

Choose the appropriate forum before starting proceedings. In Kerr v Ulsterbus [2010] NIQB 2, an injury claim begun in the High Court was transferred to the County Court and generated a separate costs dispute. The High Court dismissed the defendant’s costs appeal on the particular facts; it did not create an automatic costs rule whenever a claim is transferred. [36]

Take the pre-action exchange seriously. In Monaghan v Graham [2013] NIQB 53, a non-road-accident injury case involving an alleged fall in a cemetery, the High Court ordered pre-action disclosure and indemnity costs after an insurer persistently denied liability without reasons or relevant documents. The court exercised its discretion on those facts, under the protocol then in force. Current High Court steps come from the 2026 direction. [37] [9]

For vehicle hire, provide the information needed to explain the claim early. Kerr v Toal [2015] NIQB 83 concerned four damage-only credit-hire appeals and illustrates proportionate exchange of hire and financial information. The judge expressly distinguished his guidance from rules or practice directions and made separate orders on the particular disputes. The present County Court protocol supplies the operational pre-action steps. [38] [4]

Protect limitation and agree how the case is funded

Applies to: Northern Ireland

For an ordinary negligence claim including personal injury, Article 7 of the Limitation (Northern Ireland) Order 1989 generally allows 3 years from accrual of the cause of action or, if later, the injured person’s date of knowledge. A damage-only tort claim generally has 6 years from accrual under Article 6. The injury provision applies where the damages include personal injury; do not treat part of a mixed injury claim as having an automatic extra 3 years. Disability, knowledge and death can change the calculation. Here “disability” is a legal category covering children and certain people whose mental disorder makes them unable to manage their property and affairs; a physical injury alone is not that test. Article 50 gives the court a discretion over specified injury and fatal time limits, rather than an assured extension. Use the time-limit guide for your facts and obtain advice early. [19] [29]

A protocol letter or ongoing negotiation is not the act of bringing the court action. Have your solicitor identify the correct issue step and any service deadline before limitation expires; the protocols expressly allow protective early issue where needed. Keep the accident date, relevant knowledge dates, letter and acknowledgment dates, issue and service dates separately. [19] [12] [17] [3] [9]

Before authorising work, use paying for a Northern Ireland claim to check the retainer, insurance, legal aid eligibility, private payment and disbursements. Use Northern Ireland costs, offers and payments into court for settlement and costs decisions. If fault or evidence remains disputed, challenging a split-liability decision explains how to organise that challenge.

Deadlines and time limits

Time limitOrdinary personal injury limitationApplies to: Northern Ireland
Time limit

Generally 3 years.

When it starts

Accrual of the cause of action or the injured person’s later date of knowledge.

How to count it

Compare the two Article 7 dates and calculate 3 calendar years from the later one; obtain advice about the exact final date and the act required to bring the action. [19]

If it is missed

A late action may face a limitation defence. A claim letter is not a civil bill or writ; protect the actual issue step in time.

Which accidents and dates

Ordinary NI claims under the current 1989 Order checked 3 November 2026; accrual/knowledge, not the publication date, control.

More about this deadline: Personal injury claim: court time limit (Northern Ireland)

[12][17][19][29]

Exceptions and limits
  • Applies where damages consist of or include personal injury.

  • Article 48 modifies time for a child or a person meeting Article 47’s mental-disorder/property-and-affairs test at accrual; death and knowledge require separate checks.

  • Article 50 discretion is fact-sensitive, not automatic. [12] [17] [29]

Time limitOrdinary damage-only tort limitationApplies to: Northern Ireland
Time limit

Generally 6 years.

When it starts

Accrual of the cause of action, usually the collision causing the vehicle/property damage.

How to count it

Calculate 6 calendar years from accrual, subject to the applicable statutory exceptions; do not substitute discovery of a repair price. [19]

If it is missed

A late action may face a limitation defence; arrange the correct civil-bill or writ issue step in time.

Which accidents and dates

Current NI ordinary tort rule checked 3 November 2026; special causes of action may differ.

More about this deadline: Vehicle and property damage claim: court time limit (Northern Ireland)

[19][29]

Exceptions and limits
  • Damage-only: where the action includes personal injury, Article 7 displaces the general tort period.

  • Disability at accrual means childhood or the Article 47 mental-disorder/property-and-affairs test; other statutory qualifications require advice. Article 50 is not a general power to extend Article 6. [29]

Time limitCounty Court: unanswered letter of claimApplies to: Northern Ireland
Time limit

21 days for a reply in the ordinary domestic case.

When it starts

The County Court protocol letter of claim; record communication and receipt evidence.

How to count it

Appendix A expects acknowledgment within 21 days; paragraph 5.6 says that if no defendant, solicitor or insurer has replied within 21 days, the plaintiff should issue. The protocol does not specify a business-day calculation or a deemed-service formula for this letter. [3] [31]

If it is missed

Consider issue if no reply, after checking limitation, correct forum and service; absence of a reply does not itself establish liability.

Which accidents and dates

Current County Court protocol only; not the High Court PD 4/2026 sequence.

More about this deadline: County Court: unanswered letter of claim

[3][31]

Exceptions and limits
  • Accident outside NI or defendant outside jurisdiction: initial period extends to 42 days.

  • Paragraphs 5.7 and 7.5 permit earlier protective issue.

  • A protocol period is not an extension of statutory limitation.

Time limitCounty Court: injury investigation replyApplies to: Northern Ireland
Time limit

Maximum 3 months in the ordinary domestic case.

When it starts

Date of acknowledgment of the letter of claim by the defendant’s side.

How to count it

Count 3 calendar months from acknowledgment, not from the accident or the date you obtained a medical report; the insurer/solicitor should give the substantive liability/causation response by the end. [3]

If it is missed

The defendant’s side should admit or deny and explain any denial or contributory negligence. Do not allow the protocol wait to defeat limitation.

Which accidents and dates

Current County Court personal injury protocol checked 3 November 2026.

More about this deadline: County Court: injury investigation reply

[3]

Exceptions and limits
  • Up to 6 months if accident occurred outside NI and/or defendant outside jurisdiction.

  • Protective early issue where limitation or another reason requires it.

Time limitCounty Court: damage-only investigation replyApplies to: Northern Ireland
Time limit

Maximum 2 months in the ordinary domestic case.

When it starts

Date of acknowledgment of the damage-only RTA letter of claim.

How to count it

Count 2 calendar months from acknowledgment for the defendant’s insurer or solicitor to state and explain the liability response. [3]

If it is missed

Use the substantive response and evidence to decide settlement or issue; the expiry does not award compensation.

Which accidents and dates

Current County Court damage-only road traffic protocol checked 3 November 2026.

More about this deadline: County Court: damage-only investigation reply

[3]

Exceptions and limits
  • 4 months where accident occurred outside NI and/or defendant outside jurisdiction.

  • Protective early issue where needed; no automatic limitation extension.

Time limitHigh Court: normal pre-issue waitApplies to: Northern Ireland
Time limit

Generally after 4 months from acknowledgment if liability denied; 28 days after specified documents if admitted.

When it starts

Denial route: acknowledgment of letter of claim. Admission route: service of the paragraph 4.18 medical evidence and loss documents.

How to count it

Use the applicable branch of paragraph 10.1; the admitted-liability clock runs from service of the documents, not the admission alone. [9]

If it is missed

Premature or non-compliant issue may lead to costs or procedural penalties, including a stay.

Which accidents and dates

PD 4/2026 applies to all High Court King’s Bench injury/damage-only actions from 13 October 2026.

More about this deadline: High Court: normal pre-issue wait

[8][9]

Exceptions and limits
  • Early issue to protect position where limitation or another reason requires it.

  • Standstill requires an actual agreement; overseas cases also have different acknowledgment/investigation periods under 4.16.

  • The direction says generally; court directions and the circumstances matter. [8]

Time limitCounty Court: defendant’s notice of intention to defendApplies to: Northern Ireland
Time limit

Within 21 days from service of the civil bill.

When it starts

Service on the defendant of the civil bill under the applicable rules.

How to count it

Serve Form 42 on the other parties. Order 43 rule 17 normally starts calculation at the end of service day; all intervening days count for a 21-day period, with next-open-day protection at expiry. [14] At the same time deliver a copy of the civil bill and notice to the chief clerk; court-office defence notices require hard copy under the current guidance. [23]

If it is missed

Failure to respond risks an undefended judgment; urgent steps may be required if judgment has already been entered.

Which accidents and dates

Current NI County Court rules; already proposed by B013, not proposed again.

More about this deadline: Defendant: Northern Ireland County Court notice

[14][23]

Exceptions and limits
  • Late notice needs written consent or leave; check service method and court orders.

Time limitHigh Court: appearance and defenceApplies to: Northern Ireland
Time limit

Ordinary domestic writ: 14 days including service day for appearance; defence normally 6 weeks from the later trigger.

When it starts

Appearance: service of writ within NI. Defence: later of time limited for appearance and service of statement of claim.

How to count it

Enter an appearance within the express 14-day inclusive period for a domestic writ. For the separate 6-week defence period, use the later trigger under Order 18 rule 2 and exclude the Long Vacation unless the court directs otherwise. Order 3 governs calculation and office closure; check any court or written-consent extension. [17] [35]

If it is missed

Failure to take the required steps risks default procedures; notify the insurer/solicitor promptly.

Which accidents and dates

Current RCJ text checked 3 November 2026; earlier B013 proposal reused by mapping.

More about this deadline: Defendant: Northern Ireland High Court appearance and defence

[17][35]

Exceptions and limits
  • Service outside NI uses different appearance periods.

  • Court leave, an Order 14/86 summons and orders may change the defence period.

  • Unless the court directs otherwise, the Long Vacation is excluded for service of pleadings; written consent may extend pleading/document periods under Order 3 rule 5.

Time limitInsurer: notice of proceedings protecting statutory judgment dutyApplies to: Northern Ireland
Time limit

Before, or within 7 days after, commencement.

When it starts

Commencement of the proceedings in which the judgment is given.

How to count it

Arrange notice before commencement where possible. Otherwise the statute allows notice within 7 days after actual commencement, not after receipt of a claim letter or judgment. Establish the actual commencement date under the correct court’s rules; do not wait to resolve an uncertain final-day calculation. County Court notice uses Form 292. [13] [27]

If it is missed

Without the required notice the statutory insurer judgment duty does not arise under Article 98.

Which accidents and dates

Current Article 98A(1)(a), not the GB Road Traffic Act 1988 rule; earlier B013 proposal mapped.

More about this deadline: Northern Ireland: insurer notice protecting the statutory judgment duty

[12][13][27]

Exceptions and limits
  • Article 98 duty is subject to other Article 98A exceptions.

  • Commencement must be established under the correct court’s issue rules; do not rely on a claim letter. [12]

Time limitCounty Court: plaintiff’s initial medical evidenceApplies to: Northern Ireland
Time limit

Within 14 days after service of the defendant’s notice of intention to defend.

When it starts

Service on the plaintiff of the defendant’s notice of intention to defend.

How to count it

Plaintiff serves medical evidence substantiating the civil-bill injuries on the defendant; apply Order 43 rule 17 to procedural calculation. [16] [14]

If it is missed

Comply or seek directions promptly; the evidence and timetable affect readiness and hearing preparation.

Which accidents and dates

Current County Court Order 24 rule 39; injury claims only.

More about this deadline: County Court: plaintiff’s initial medical evidence

[14][16]

Exceptions and limits
  • Court may enlarge or abridge procedural time under Order 43 rule 10.

  • This is the initial substantiating evidence rule, not permission to withhold later relevant evidence.

Your checklist

  • Identify the right court and defendant before choosing a civil bill or writ. [11] [12] [17]

    Applies to: Northern Ireland
  • Send a detailed letter of claim and copy the known insurer; retain its sending, receipt and acknowledgment dates. [2] [3]

    Applies to: Northern Ireland
  • Collect medical evidence, photographs, repair and hire papers, receipts and proof of financial loss relevant to what you claim. [4] [16]

    Applies to: Northern Ireland
  • Check limitation before waiting for a protocol reply, and arrange protective issue if required. [19] [3] [9]

    Applies to: Northern Ireland
  • Arrange valid service and the separate insurer notice of proceedings; keep evidence of both. [12] [13] [27]

    Applies to: Northern Ireland
  • Serve the required response promptly if you defend, and comply with the applicable court timetable. [14] [17]

    Applies to: Northern Ireland
  • Consider settlement or mediation and keep a record of the steps taken. [5] [9]

    Applies to: Northern Ireland

Common questions

Which injury-claim route should I use when OIC does not apply to my Northern Ireland accident?Applies to: Northern Ireland

Use the Northern Ireland pre-action and court route. Official Injury Claim covers qualifying accidents in England and Wales. For an ordinary Northern Ireland injury claim, follow the County Court protocol if a civil bill is appropriate, or the High Court’s separate Practice Direction 4 of 2026 for a High Court action. The current general County Court limit is £30,000, but check jurisdiction and valuation as well as amount; the High Court ordinarily starts an accident damages action by writ. [21] [1] [6] [11] [17]

Which Northern Ireland court procedure and time limits do I need to check?Applies to: Northern Ireland

Check whether you need a County Court civil bill or High Court writ, the applicable protocol, limitation, valid issue, service and the defendant’s response. Injury claims ordinarily have 3 years from accrual or later knowledge; damage-only tort claims ordinarily have 6 years from accrual, with qualifications including children and certain people unable through mental disorder to manage their property and affairs. A County Court defendant intending to defend normally serves Form 42 within 21 days from service. A High Court writ served within Northern Ireland normally allows 14 days including service day for appearance; the defence normally follows within 6 weeks after the time limited for appearance or service of the statement of claim, whichever is later. Unless the court directs otherwise, the Long Vacation is excluded for serving pleadings, including the defence. Court orders, written-consent extensions and overseas service can change procedural periods. [35] Get the time-limit guide checked against your facts before relying on a date. [12] [17] [19] [14]

Can I use Northern Ireland small claims for my damage-only car-accident claim?Applies to: Northern Ireland

No. Order 26 rule 2 excludes damages in respect of a road traffic accident as well as personal injury damages. This includes a damage-only collision claim below the usual £5,000 small-claims ceiling. If your claim belongs in the County Court, use the ordinary civil-bill route after the County Court pre-action protocol; a low repair cost does not make it eligible for small claims. [10] [30] [12] [1]

What should happen before I issue a civil bill for my injury or damage-only accident claim?Applies to: Northern Ireland

Follow the County Court protocol: send a detailed letter of claim, copy the known insurer, and provide the relevant injury, loss and vehicle or hire information. If there is no reply within 21 days the protocol says to issue; after acknowledgment, the defendant’s insurer or solicitor has up to 3 months to investigate injury or 2 months for damage-only road traffic claims. If the accident or defendant is outside Northern Ireland, the protocol extends these periods. Exchange relevant evidence and consider settlement or ADR; where liability and causation are admitted, disclose special losses, supporting papers and available medical evidence before issue. Limitation or another need to protect your position can justify earlier issue. These are County Court steps; the High Court uses its own direction. [1] [2] [3] [4] [5] [6]

Key points

Show the 5 key points of this guide
  • Northern Ireland small claims excludes RTA damages, including damage-only claims below £5,000. [10] [30]

    Applies to: Northern Ireland
  • County Court pre-action injury and damage-only investigation periods run from acknowledgment and differ. [3]

    Applies to: Northern Ireland
  • The High Court has used PD 4/2026 for all King’s Bench injury and damage-only actions since 13 October 2026. [6]

    Applies to: Northern Ireland
  • The act of issuing a civil bill is defined by Order 6 rule 1 and must be protected within limitation. [12] [19]

    Applies to: Northern Ireland
  • The relevant motor insurer needs separate notice of proceedings within Article 98A’s period for the statutory judgment duty. [13] [27]

    Applies to: Northern Ireland

Check which dates control your time limit

Court decisions in this guide

Kerr (Ellen) v Ulsterbus LtdShould the High Court interfere with the County Court judge’s decision on reserved remittal-appeal costs in an RTA claim?[2010] NIQB 2 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 6 January 2010 · Appeal status not confirmedMonaghan (Richard) v The Very Reverend Graham sued on behalf of the Trustees of Milltown CemeteryCould the court order pre-action discovery and indemnity costs after an insurer denied liability without reasons or relevant documents?[2013] NIQB 53 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 3 May 2013 · Appeal status not confirmedKerr (Ann) v Conor Toal; Declan Gordon v Vera Best and Iain Best; Margaret Gregory v Olivia Cashel O’Farrell; John Chadwick v Pawel KaczorWhat proportionate information exchange and discovery were appropriate in four damage-only credit-hire appeals?[2015] NIQB 83 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 12 February 2015 · Appeal status not confirmedQuinn (Miceal William) and Quinn (William Kevin) v McAleenan (Kevin) and McConville (Michael)Should the court set aside regular default judgments where the defendants had delayed and failed to show a convincing arguable defence?[2010] NIQB 31 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 3 March 2010 · Appeal status not confirmedJohn Donnelly Developments Limited v Niall Curran and Patricia CurranHow should the court deal with a building-contract trial in which issues had not been properly defined and amendments became necessary?[2013] NIQB 66 · High Court of Justice in Northern Ireland, Queen’s Bench Division (Commercial Action) · Northern Ireland · 29 May 2013 · Appeal status not confirmedSouth Eastern Health and Social Care Trust v Colin Flannagan and Capper Trading LimitedCould a public health-body plaintiff recover the full credit-hire rate, and what role did proof of impecuniosity and reasonable basic hire play?[2015] NIQB 30 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 15 April 2015 · Appeal status not confirmed

Organisations

Northern Ireland Courts and Tribunals Service (NICTS)The Northern Ireland Courts and Tribunals Service is an agency of the Department of Justice.NORTHERN IRELANDOfficial Injury Claim service (OIC)Official Injury Claim is the service developed by the Motor Insurers’ Bureau on behalf of the Ministry of Justice for the England and Wales RTA small-claims process.ENGLAND AND WALES

This guide describes the rules as they stood when it was last updated, on 3 November 2026. If your accident happened before then, some of the rules may have been different.

Sources

  1. Source 1: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 1.1; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 1.3; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 2.1Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the 3 quoted extracts
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 1.1
    1.1 This Pre-Action Protocol applies to all cases involving claims in personal injury litigation and damage-only road traffic accidents.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 1.3
    1.3 The court will treat the standards set out in this protocol as the normal reasonable approach of parties in cases involving claims in personal injury litigation and damage-only road traffic accidents. The courts will expect the parties to have complied with this protocol before proceedings are issued.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 2.1
    2.1 If a party to the claim does not have a legal representative they should still, insofar as reasonably possible, fully comply with this protocol. If a party to a claim becomes aware that another party is a litigant in person, they should send a copy of this protocol to the litigant in person at the earliest opportunity.
  2. Source 2: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.1; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.2; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.4; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 6.1Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.1
    5.1 After the writing of any preliminary notification letter to the defendant the plaintiff’s solicitors should send to any legal or corporate representative of the proposed defendant a detailed letter of claim as soon as sufficient information is available to substantiate a realistic claim and before issues of quantum are addressed in detail.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.2
    5.2 The letter of claim shall contain the following information: (a) a clear summary of the facts upon which the claim is based; (b) an indication of the nature of any injuries suffered; (c) details of any financial loss incurred even where such details are necessarily provisional; (d) the plaintiff’s full address and post code; (e) the name and address of any hospital attended by the plaintiff, whether or not treatment was afforded thereat, together with the plaintiff’s hospital reference number when available.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.4
    5.4 The letter of claim should seek the details of any relevant insurer and, if the identity of the insurer is known, a copy of the letter of claim should be sent directly to the insurer.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 6.1
    6.1 If the plaintiff is claiming vehicle damage and or the cost of a replacement vehicle they will provide: (a) the plaintiff’s date of birth; (b) the details of heads of claim to be presented if available; (c) the plaintiff’s impecuniosity position if ascertainable; (d) details of whether the vehicle is roadworthy or drivable; (e) the plaintiff’s occupation, if relevant. For example, if the plaintiff uses their vehicle as a taxi or primarily for business purposes.
  3. Source 3: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.6; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.7; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.1; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.2; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.3; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.4; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.5Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the 7 quoted extracts
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.6
    5.6 If there has been no reply by the defendant or any solicitor or insurer within 21 days, the plaintiff should proceed to issue proceedings.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 5.7
    5.7 If there is a limitation problem or some other reason as to why the plaintiff’s position needs to be protected then the plaintiff may issue proceedings before the expiration of 21 days.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.1
    7.1 In a personal injury claim the defendant’s solicitor/insurer will have a maximum of 3 months from the date of acknowledgement of the letter of claim to investigate. No later than the end of that period the defendant’s insurer/solicitors should reply, stating whether liability and/or causation is admitted or denied as appropriate and if denied, stating with sufficient clarity and detail so that the plaintiff is made aware of the defendant’s case, including if the fault lies with, or an indemnity is claimed from another. If contributory negligence is being alleged by the defendant, details should be provided of what is alleged and upon what basis.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.2
    7.2 In a road-traffic damage only claim the defendant’s solicitor/insurer will have a maximum of 2 months from the date of acknowledgement of the letter of claim to investigate. No later than the end of that period the defendant’s insurer/solicitors should reply, stating whether liability is admitted or denied as appropriate and if denied, stating with sufficient clarity and detail so that the plaintiff is made aware of the defendant’s case, including if the fault lies with, or an indemnity is claimed from another. If contributory negligence is being alleged by the defendant, details should be provided of what is alleged and upon what basis.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.3
    7.3 In a personal injury claim where the relevant accident occurred outside Northern Ireland and/or where the defendant is outside the jurisdiction, the time periods of 21 days and 3 months will be extended up to 42 days and 6 months.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.4
    7.4 In a road-traffic damage only claim where the relevant accident occurred outside Northern Ireland and/or where the Defendant is outside the jurisdiction, the time periods of 21 days and 2 months will be extended to 42 days and 4 months.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.5
    7.5 If there is a limitation problem or some other reason as to why the plaintiff’s position needs to be protected, then the plaintiff may issue proceedings before the expiration of the above time periods.
  4. Source 4: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.7; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.1; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.2; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.3; NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.9Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the 5 quoted extracts
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 7.7
    7.7 Where liability is admitted, the defendant/insurer will be bound by this admission. The exception of this will be when, subsequently, there is evidence that the claim is fraudulent.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.1
    8.1 If the defendant denies liability and/or causation, he ought to enclose with the letter of reply any documents in his possession which are material and relevant to the issues between the parties and which would be likely to be ordered to be disclosed by the court either on an application for pre-action discovery or on discovery during proceedings. The aim of early discovery of documents by the defendant is not to encourage “fishing expeditions” by the plaintiff, but to promote an early exchange of relevant information to help in clarifying or resolving issues in dispute. The plaintiff’s solicitor can assist by identifying in the letter of claim or in a subsequent letter the particular categories of documents which are considered to be relevant.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.2
    8.2 Where the defendant admits liability and causation the plaintiff solicitor should, prior to issuing proceedings, disclose to the defendant particulars of the special losses that they are seeking to recover, the documents supporting same and, if applicable, any available medical evidence on which the plaintiff intends to rely.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.3
    8.3 If the plaintiff is claiming vehicle damage and/or the cost of a replacement vehicle the plaintiff will provide the following information, if available: (a) the repair invoice; (b) any depreciation report; (c) the recovery agreement and invoice; (d) the storage agreement and invoice; (e) confirmation of whether the plaintiff has transferred their own comprehensive insurance, and if so, they will provide temporary insurance invoices; (f) the hire invoice and hire agreements; (g) proof that they held a valid licence for 3 years prior to the accident; (h) confirmation of whether they held any penalty points at the time of hire; (i) confirm if they need to potentially travel outside of Northern Ireland; (j) confirmation of whether the vehicle was required for purposes of taxiing, towing, or storing livestock; (k) the details of additional drivers, their relationship to the plaintiff, convictions, penalty points and length of time that additional driver has held a licence; (l) the reasons for high-risk charges if applicable.
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 8.9
    8.9 If the plaintiff is relying on impecuniosity, they will provide the following information, if available: (a) three months bank/building society statements; (b) three months credit union savings statements or the equivalent; (c) the monthly cost of servicing any debts/loans; (d) details of outgoings at the time of the accident; (e) details of their earnings at the time of the accident, and if the plaintiff’s earnings are not paid into a bank account, then 3 months’ pay slips will be provided.
  5. Source 5: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 10.1Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), para. 10.1
    10.1 The parties should consider whether some form of alternative dispute resolution procedure would be more suitable than litigation, and if so, endeavour to agree which form to adopt. During the course of any litigation both the plaintiff and the defendant may be required by the court to produce evidence that alternative means of resolving their dispute have been considered. Different forms of alternative dispute resolution are available and a mediation service is provided by the Law Society of Northern Ireland. It is expressly recognised that no party can or should be forced to mediate or enter into any form of alternative dispute resolution.
  6. Source 6: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · NI High Court Practice Direction 4 of 2026 (PI and damage only actions), Application and Scope (cover page)Practice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), Application and Scope (cover page)
    This Practice Direction applies to all personal injury and damage only civil litigation actions in the King’s Bench Division of the High Court of Justice in Northern Ireland. This Practice Direction revokes and replaces Practice Direction 01/2008 Personal Injury Litigation and the Pre-Action Protocol for Personal Injury Litigation dated 1st April 2008. This Practice Direction has effect from 13 October 2026. Signed this 13th day of October 2026 The Right Honourable Dame Siobhan Keegan Lady Chief Justice
  7. Source 7: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.2; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.3; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.18Practice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the 3 quoted extracts
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.2
    4.2 The letter of claim should contain the following information: (a) the plaintiff’s full name and address; (b) the plaintiff’s date of birth; (c) the plaintiff’s national insurance number; (d) the date, time and place of the accident or incident giving rise to the claim; (e) a clear summary of the facts upon which the claim is based; (f) details of the person or entity said to be responsible and their relationship to the plaintiff; (g) details of any other prospective defendant; (h) an indication of the nature of any injuries suffered, including where there is any psychiatric or psychological aspect; (i) details of any financial loss incurred, even where such details are necessarily provisional; (j) the name and address of any hospital attended by the plaintiff, whether or not treatment was afforded there, together with the plaintiff’s hospital reference number when available.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.3
    4.3 If the plaintiff is claiming for vehicle damage, the cost of hire of a replacement vehicle and/or storage charges they will provide, if available and if relevant: (a) details of heads of claim to be presented; (b) the plaintiff’s impecuniosity position; (c) confirmation of whether the plaintiff is VAT registered; (d) details of whether the vehicle is roadworthy, drivable and/or still in storage; (e) details of the plaintiff’s occupation, if relevant (for example - if the plaintiff uses their vehicle as a taxi or primarily for business); (f) vehicle damage and/or the cost of a replacement vehicle; (g) vehicle repairs under a ‘credit repair’ agreement; (h) the total loss of their vehicle where the process is being dealt with by an accident management company; (i) vehicle damage/total loss which is being dealt with under the terms of their comprehensive policy of insurance. (j) the repair invoice; (k) any diminution in market value report; (l) the recovery agreement and invoice; (m) the storage agreement and invoice; (n) confirmation of whether the plaintiff has transferred their own comprehensive insurance, and if so, they will provide temporary insurance invoices; (o) the hire invoice and hire agreements; (p) proof that they held a valid licence for 3 years prior to the accident; (q) confirmation of whether they held any penalty points at the time of hire; (r) confirm if they will potentially travel outside of Northern Ireland; (s) confirmation of whether the vehicle was required for purposes of taxiing, towing, or storing livestock; (t) the details of additional drivers, their relationship to the plaintiff, convictions, penalty points and length of time that additional driver has held a licence; (u) the reasons for high-risk charges.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.18
    4.18 If the defendant admits liability, the plaintiff should proceed to obtain his medical evidence and send his available medical evidence to the defendant’s representative. The plaintiff should send to the defendant as soon as is reasonably practicable, a schedule of any past and future expenses and losses which he claims (including all relevant receipts, invoices, vouchers etc) even if the schedule is necessarily provisional. The schedule should contain as much detail as is reasonably practicable and should identify those losses that are ongoing. If the schedule is likely to be updated before the case is concluded, it should say so. The plaintiff should keep the defendant informed as to the rate at which his financial loss is progressing throughout the pre-action period so far as is practicable.
  8. Source 8: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.13; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.14; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.15; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.16; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.17Practice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the 5 quoted extracts
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.13
    4.13 The defendant should provide an acknowledgement of the letter of claim and identify any relevant insurer within 21 days.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.14
    4.14 If the defendant is aware of any significant omissions from the letter of claim they should identify them specifically within the letter of acknowledgement.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.15
    4.15 In the vast majority of cases, the defendant will have a maximum three months from the date of acknowledgement of the letter of claim to investigate. If a defendant cannot meet this timescale, the defendant shall set out in advance of the expiration of this period, the reasons why the timescale cannot be met, what further investigations are to be carried out, and what further period of time is required to comply.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.16
    4.16 Where the relevant accident occurred outside Northern Ireland and/or where the defendant is outside the jurisdiction, the time periods above of 21 days and three months will normally be extended up to 42 days and six months respectively.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 4.17
    4.17 The response to the letter of claim should include the following: (a) Whether liability is admitted or denied, or what aspects of the plaintiff’s allegations require further investigation; (b) if liability and/or causation is denied, the defendant should explain with sufficient clarity and precision the reasons for such denial - including an indication of any facts upon which the defendant is likely to rely upon in support of any substantive defence; (c) if contributory negligence is being alleged by the defendant, details should be provided of what is alleged and on what basis.
  9. Source 9: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 7.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 9.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 10.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 10.2Practice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 7.1
    7.1 Litigation should be a last resort. The parties should consider whether negotiation or some other form of Alternative Dispute Resolution (ADR) might enable them to resolve their dispute without commencing proceedings, and if so, endeavour to agree which form to adopt. Where one of the parties involved is a personal litigant, it is important to understand that it is normal for the other side to discuss the claim and seek resolution in advance of, or instead of, going to court. The court may seek evidence of attempts to do this when a full hearing occurs.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 9.1
    9.1 In the context of litigation a standstill agreement is an agreement between the intended parties or their representatives which has the practical effect of suspending or extending a statutory or a contractual limitation period. For example, a standstill agreement duly executed between the intended parties to litigation has the potential to avoid the issue of protective proceedings where a matter remains under investigation, thereby facilitating the completion of the said investigation and avoiding potentially unnecessary expenditure and stress on the parties associated with proceedings.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 10.1
    10.1 Once a decision has been taken by the plaintiff and/or their advisors that proceedings should be commenced, unless there is a limitation problem or some other reason as to why the proposed plaintiff’s position needs to be protected by early issue where liability is denied, proceedings should not generally be issued until after four months from the date of acknowledgement of the letter of claim by the proposed defendant(s)/representatives (note paragraph 6.1 applies). Or where liability is admitted by the defendant, until 28 days after service of the documents referred to in paragraph 4.18. Parties’ attention is drawn to Order 18 of the CoJ Rules governing the service of pleadings.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 10.2
    10.2 The court may consider costs penalties and/or procedural penalties for noncompliance, such as a stay in proceedings if there is no letter of claim or no letter of acknowledgement and/or substantive response from the proposed defendant(s).
  10. Source 10: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · Order 26 rule 2(a)–(b)Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    County Court Rules (Northern Ireland) 1981, Order 26 r. 2
    No small claims application shall be made with regard to any claim which— (a) is for damages for personal injuries; (b) is for damages in respect of a road traffic accident;
  11. Source 11: County Courts (Northern Ireland) Order 1980Act · legislation.gov.uk (The National Archives); King's Printer · County Courts (Northern Ireland) Order 1980, art. 10; County Courts (Northern Ireland) Order 1980, art. 30Latest revised version on legislation.gov.uk, valid from 2022-10-03; editorially updated 2024-10-29 · read on 3 November 2026Official textOur page on this source
    Show the 2 quoted extracts
    County Courts (Northern Ireland) Order 1980, art. 10
    (1) Subject to the provisions of this Part, a county court shall have jurisdiction to hear and determine any action in which the amount claimed, or the value of specific chattels claimed, does not exceed £30,000 , including (but without prejudice to the generality of the foregoing provisions of this paragraph) any action in which a balance not exceeding £30,000 is claimed— (a) on foot of an account (including a partnership account); (b) after allowances made for any amount admitted by the plaintiff to be due by him to the defendant (whether by way of set-off or on foot of a counterclaim or otherwise); or (c) after the abandonment by the plaintiff of any sum by which the amount alleged to be due to him by the defendant exceeds £30,000 , so, however, that a decree in respect of any cause of action to which this sub-paragraph applies shall be, and be expressed to be, in full discharge of all demands in respect of that cause of action. (2) A county court shall not have jurisdiction to hear any action claiming damages exceeding £3,000 in respect of libel or slander. (3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (3A) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (4) A county court shall not have jurisdiction to hear any Admiralty cause or matter. (5) A county court shall not have jurisdiction to hear any action in which the title to any toll, fair, market or franchise is in question. (6) A claim for the recovery of any rent or other sum not exceeding £15,000 due in respect of the use and occupation of any land may be joined with, and heard and determined together with, a claim under this Part for the recovery of that land.
    County Courts (Northern Ireland) Order 1980, art. 30
    (1) Subject to paragraph (3), any action in which the amount claimed, or the value of specific chattels claimed, does not exceed £10,000 shall, save as otherwise provided by county court rules, be heard and determined by a circuit registrar in accordance with those rules. (2) Any order, decision or determination made by a district judge under this Article (other than one made in dealing with a claim by way of arbitration under paragraph (3)) shall be embodied in a decree which for all purposes (including the right of appeal under Part VI) shall have the like effect as a decree pronounced by a county court judge. (3) Where in any action to which paragraph (1) applies the amount claimed, or the value of specific chattels claimed, does not exceed £5,000 the circuit registrar shall, save as otherwise provided by county court rules, deal with the claim by way of arbitration in accordance with those rules.
  12. Source 12: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · County Court Rules (Northern Ireland) 1981, Order 5 r. 1; County Court Rules (Northern Ireland) 1981, Order 5 r. 2; County Court Rules (Northern Ireland) 1981, Order 6 r. 1Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    County Court Rules (Northern Ireland) 1981, Order 5 r. 1
    (1) Except as otherwise provided by an enactment or these Rules, proceedings in a county court shall be commenced by a civil bill in such one of the Forms 9 to 32 as may be appropriate. (2) Every civil bill shall be signed by the plaintiff or by his solicitor or a partner or duly authorised employee of his solicitor. (3) A civil bill commencing proceedings in a title action or for ejectment on the title shall be headed with the words “Title Jurisdiction”. (4) A civil bill commencing proceedings within the equity jurisdiction of the court (in these Rules referred to as an “equity civil bill”) shall be headed with the words “Equity Civil Bill”. (5) An ordinary or ejectment civil bill shall bear an endorsement in Form 10 or Form 13, as may be appropriate.
    County Court Rules (Northern Ireland) 1981, Order 5 r. 2
    (1) The plaintiff shall set out in his civil bill particulars of his claim. (1A) Where the plaintiff claims interest under Article 45A of the Order or otherwise the particulars of claim set out in his civil bill shall contain a statement to that effect] [ and shall specify the amount claimed as interest with the degree of particularity required by [ Rule 1A of Order 33].]
    County Court Rules (Northern Ireland) 1981, Order 6 r. 1
    A civil bill shall be deemed to have been issued— (a) so soon as it has been received by a process server (or other person authorised by this Order) for service on any defendant; or (b) so soon as service of it has been accepted by a solicitor under Rule 3(4); or (c) without prejudice to paragraphs (a) and (b), so soon as an order for service of a civil bill has been made under Rule 6(2) or so soon as service declared sufficient under Rule 7 has been effected or so soon as service of a civil bill to which Rule 11 applies has been effected in accordance with that Rule; or (d) where service is by post, as soon as it has been posted; or (e) in an action such as is referred to in Rule 9(2) or Order 3 (where a civil bill is issued against “the personal representatives of AB deceased”) when a copy thereof is filed in the Office.
    County Court Rules (Northern Ireland) 1981, Order 5 r. 2
    (6) Where a plaintiff desires to abandon, under Article 10(1) of the Order, the excess of his claim over [ £30,000], the abandonment of the excess shall be entered at the end of the particulars.
  13. Source 13: Road Traffic (Northern Ireland) Order 1981Act · legislation.gov.uk (The National Archives); King's Printer · Article 98A(1)(a)Latest revised version on legislation.gov.uk, valid from 2025-04-01; editorially updated 2025-05-19 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    Road Traffic (Northern Ireland) Order 1981, art. 98A
    (1) No sum shall be payable by an insurer under Article 98— (a) in respect of any judgment unless, before or within seven days after the commencement of the proceedings in which the judgment was given, the insurer had notice of the bringing of the proceedings;
  14. Source 14: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · County Court Rules (Northern Ireland) 1981, Order 8 r. 2; County Court Rules (Northern Ireland) 1981, Order 8 r. 4; County Court Rules (Northern Ireland) 1981, Order 43 r. 17Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the 3 quoted extracts
    County Court Rules (Northern Ireland) 1981, Order 8 r. 2
    (1) Without prejudice to paragraph (2), in any proceedings commenced by civil bill which a defendant intends to defend he shall, within a period of 21 days from the date of service upon him of the civil bill, serve on the other party or parties to the proceedings a notice of intention to defend in Form 42. (2) A defendant shall not serve a notice of intention to defend after the expiration of a period of 21 days after service upon him of the civil bill except with the consent in writing of the other party or parties or with the leave of the judge or the district judge as the case may be. (3) Service by a defendant of a notice of intention to defend shall not prevent a defendant from raising any issue or defence which he would otherwise be entitled to raise concerning the civil bill, or issue or service of the civil bill, or the jurisdiction of the court.
    County Court Rules (Northern Ireland) 1981, Order 8 r. 4
    In every proceedings commenced by civil bill in which the defendant serves a notice of intention to defend the defendant shall also at the same time as he serves the notice of intention to defend on the other party or parties to the proceedings deliver to the chief clerk a copy of the civil bill and of the notice of intention to defend.] [ . . .]
    County Court Rules (Northern Ireland) 1981, Order 43 r. 17
    Without prejudice to section 39 of the Interpretation Act (Northern Ireland) 1954— (a) where anything is required by these Orders to be done within a specified period of or after the happening of a particular event, the period shall be computed from the end of the day on which the event happens unless the period is expressed to be inclusive of such day; (b) where anything is required by these Orders to be done within a period not exceeding three days or where a period not exceeding three days is required by these Orders to elapse between the doing of an act and the happening of a particular event, no Saturday or Sunday nor any day on which the Office is closed shall be included in the computation of that period; (c) where the time prescribed for doing any act expired on a Saturday or a Sunday or any day on which the Office is closed, the act shall be in time if done on the next day on which the Office is open.
  15. Source 15: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · County Court Rules (Northern Ireland) 1981, Order 8 r. 3Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    County Court Rules (Northern Ireland) 1981, Order 8 r. 3
    (1) In any proceedings commenced by civil bill in which a notice of intention to defend has been served the plaintiff shall, [subject to paragraph (1A) and] after the conclusion of all interlocutory matters, request the chief clerk to enter the proceedings for hearing by delivery to the chief clerk at his office of a certificate of readiness in Form 43 and shall, at the same time, cause to be served on the other party or parties to the proceedings a copy of the certificate of readiness. (1A) [ Subject to paragraph (1B),] a certificate of readiness may not be delivered to the chief clerk until the expiry of 21 days following the date of service of the notice of intention to defend.] (1B) The plaintiff must notify the defendant in writing of his intention to lodge the certificate of readiness no later than 14 days prior to lodging the certificate.] (2) In any proceedings in which a notice of intention to defend has been served the chief clerk shall, if no certificate of readiness has been delivered to him within a period of 6 months immediately following the date of service of the notice of intention to defend, list the proceedings before the judge [) or district judge as the case may be] and notify the parties accordingly and the judge [ or district judge as the case may be] may issue such directions concerning the future conduct of any such proceedings as he considers appropriate [ including, in particular, an order that the proceedings be stayed or dismissed.]
  16. Source 16: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · County Court Rules (Northern Ireland) 1981, Order 24 r. 2; County Court Rules (Northern Ireland) 1981, Order 24 r. 2B; County Court Rules (Northern Ireland) 1981, Order 24 r. 39; County Court Rules (Northern Ireland) 1981, Order 43 r. 10Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    County Court Rules (Northern Ireland) 1981, Order 24 r. 2
    (1) Save as otherwise provided by these Rules, the evidence of witnesses at the hearing of any action or matter shall be taken orally on oath, and where by these Rules evidence is required or permitted to be taken by affidavit, it shall nevertheless be taken orally on oath if [ the judge or district judge as the case may be], on any application before or at the hearing, so directs. (2) The court may allow a witness to give evidence through a video link or by any other method of direct communication.]
    County Court Rules (Northern Ireland) 1981, Order 24 r. 2B
    (1) Unless [ the judge or district judge as the case may be] otherwise orders and subject to paragraph (2), [ any report or other accompanying or supplemental document served or disclosed pursuant to the provisions of Part III or rule 2D of this Order] or any map, plan, drawing, photograph or model produced pursuant to the provisions of Rule 2A by any party to proceedings to the other parties may be given in evidence without further proof at the hearing or an assessment of damages by the party who has disclosed or produced it. (2) Any other party may, on giving sufficient notice to the party making the disclosure or production specified in paragraph (1), require the maker of any such [ . . .] report to give oral evidence or require any such map, plan, drawing, photograph or model to be proved, and in any such case paragraph (1) shall not apply. (3) Where a medical witness or other expert witness is, unable to attend court to give oral evidence at the hearing or an assessment of damages [ the judge or district judge as the case may be] may direct that his written report or reports may be given in evidence or that any such map, plan, drawing, photograph or model may be admitted in evidence without further proof thereof, and in such case paragraph (2) shall not apply.
    County Court Rules (Northern Ireland) 1981, Order 24 r. 39
    The plaintiff shall serve on the defendant medical evidence substantiating the personal injuries alleged in the civil bill within 14 days after service upon him of the defendant’s notice of intention to defend.
    County Court Rules (Northern Ireland) 1981, Order 43 r. 10
    [ The judge or district judge as the case may be] may, upon such terms, if any, as he may think reasonable, enlarge or abridge any of the times fixed by these Rules for taking any step, or filing or sending any document, or giving any notice in any proceedings; and where any person has failed to take any step, or to file or serve any document, or to give any notice within the time or in the manner prescribed by these rules, [ the judge or district judge as the case may be] may, upon the application of such person, and if he thinks sufficient excuse exists for such failure, and upon such terms as, to costs or otherwise as he thinks fit, declare the taking of such step, or the filing or serving of such document, or the giving of such notice so done or effected, to be sufficient.
  17. Source 17: The Rules of the Court of Judicature (Northern Ireland) (Revision) 1980Court rules · legislation.gov.uk (The National Archives); King's Printer · Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 5 r. 2; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 12 r. 5; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 18 r. 2; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 6 r. 7Latest revised version on legislation.gov.uk, valid from 2025-07-11; editorially updated 2025-08-27 · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 5 r. 2
    Subject to the provisions of any statutory provision or of these Rules, by virtue of which any proceedings are expressly required to be begun otherwise than by writ, the following proceedings must, notwithstanding anything in rule 4, be begun by writ, that is to say, proceedings— (a) in which a claim is made by the plaintiff for any relief or remedy for any tort, other than trespass to land; (b) in which a claim made by the plaintiff is based on an allegation of fraud; (c) in which a claim is made by the plaintiff for damages for breach of duty (whether the duty exists by virtue of a contract or of a provision made by or under a statutory provision or independently of any contract or any such provision), where the damages claimed consist of or include damages in respect of the death of any person or in respect of personal injuries to any person or in respect of damage to any property; (d) in which a claim is made by the plaintiff in respect of the infringement of a patent. [E.r. 2]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 12 r. 5
    Reference in these Rules to the time limited for appearing are, references— (a) in the case of a writ served within the jurisdiction, to 14 days after service of the writ (including the day of service) or, where that time has been extended by or by virtue of these Rules, to that time as so extended; and (b) in the case of a writ, or notice of a writ, served out of the jurisdiction, to the time limited under Order 10 rule 2(2), Order 11 rule 1(3), or Order 11 rule 4(4), or, where that time has been extended as, aforesaid, to that time as so extended. [E.r. 5]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 18 r. 2
    (1) Subject to paragraph (2), a defendant who enters an appearance in, and intends to defend, an action must, unless the Court gives leave to the contrary, serve a defence on the plaintiff before the expiration of [ 6 weeks] after the time limited for appearing or after the statement of claim is served on him, whichever is the later. (2) If a summons under Order 14 rule 1 or under Order 86 rule 1 is served on a defendant before he serves his defence, paragraph (1) shall not have effect in relation to him unless by the order made on the summons he is given leave to defend the action and, in that case, shall have effect as if it required him to serve his defence within [ 6 weeks] after the making of the order or within such other period as may be specified therein. [E.r. 2]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 6 r. 7
    (1) For the purpose of service, a writ (other than a concurrent writ) is valid in the first instance for 12 months beginning with the date of its issue and a concurrent writ is valid in the first instance for the period of validity of the original writ which is unexpired at the date of issue of the concurrent writ. (2) Where a writ has not been served on a defendant, the Court may by order extend the validity of the writ from time to time for such period, not exceeding 12 months at any one time, beginning with the day next following that on which it would otherwise expire, as may be specified in the order, if an application for extension is made to the Court before that day or such later day (if any) as the Court may allow. (3) Before a writ, the validity of which has been extended under this rule, is served, it must be sealed with a seal showing a period for which the validity of the writ has been so extended. (4) Where the validity of a writ is extended by order made under this rule, the order shall operate in relation to any other writ (whether original or concurrent) issued in the same action which has not been served so as to extend the validity of that other writ until the expiration of the period specified in the order. [E.r. 8]
  18. Source 18: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 12.4; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 13.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 17.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 20.1; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 20.2; NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 23.1Practice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the 6 quoted extracts
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 12.4
    12.4 Parties are reminded that, in advance of the first review before the Master, the First Review Questionnaire shall be completed and submitted to the court at the review or in advance by email to the court office. In addition, the plaintiff shall ensure that the court review fee is paid before the listing of the first review and the parties should ensure that they check the updated court list to obtain accurate listing details, court lists for the Court of Judicature can be accessed at the following link; Court of Judicature List | Department of Justice and parties are reminded that lists are subject to change up until 5pm each day. In cases where liability is admitted by the defendant, the defendant is encouraged to discharge the first review court fee.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 13.1
    13.1 All personal injury and damage only actions will be listed for first review before the Master nine months after the filing of the memorandum of appearance. All parties who appear at such a review are reminded of what is expected of them (see paragraph 12.1 above). The purpose of the review is to ascertain the readiness of the action for setting down and trial.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 17.1
    17.1 The parties shall promptly disclose properly discoverable documents in their possession which would be likely to be ordered to be disclosed by the court either on an application for pre-proceedings discovery, or on discovery during the proceedings.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 20.1
    20.1 Remittal or removal applications should not be brought without providing the opposing party with the opportunity to consider the evidence put forward in support of the application. If consent is sought from the plaintiff’s solicitors for remittal, the plaintiff’s solicitors should indicate whether their medical or other expert evidence is complete.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 20.2
    20.2 Remittal or removal applications should not normally be brought where the opposing party indicates that further medical or other expert evidence is awaited.
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), para. 23.1
    23.1 The trial date for the hearing of a personal injury or damage only action will be fixed to permit sufficient time for the parties to comply with all directions of the court, so as to ensure that when the matter is listed for trial the case is ready to proceed. The case will not be fixed for trial until it has been set down and the appropriate court fees paid, once the case has been set down it shall be reviewed by the Judge within four to six weeks or earlier on request. Where cases are set down prematurely they may be taken out of the Judge’s list and referred back to the Master for review either on request by the parties or the court’s own motion.
  19. Source 19: The Limitation (Northern Ireland) Order 1989Act · legislation.gov.uk (The National Archives); King's Printer · Limitation (Northern Ireland) Order 1989, art. 6; Limitation (Northern Ireland) Order 1989, art. 7; Limitation (Northern Ireland) Order 1989, art. 47; Limitation (Northern Ireland) Order 1989, art. 48Latest revised version on legislation.gov.uk, valid from 2026-04-06; editorially updated 2026-05-11 · read on 3 November 2026Official textOur page on this source
    Show the 7 quoted extracts
    Limitation (Northern Ireland) Order 1989, art. 6
    (1) Subject to paragraph (2) and to Articles 7 and 9 and 11 to 13, an action founded on tort may not be brought after the expiration of six years from the date on which the cause of action accrued. (2) Subject to Article 51, an action for damages for— (a) libel or slander; or (b) slander of title, slander of goods or other malicious falsehood, may not be brought after the expiration of one year from the date on which the cause of action accrued.
    Limitation (Northern Ireland) Order 1989, art. 7
    (1) This Article applies to any action for damages for negligence, nuisance or breach of duty (whether the duty exists by virtue of a contract or of provision made by or under a statute or independently of any contract or any such provision) where the damages claimed by the plaintiff for the negligence, nuisance or breach of duty consist of or include damages in respect of personal injuries to the plaintiff or any other person. (1A) This Article does not apply to any action brought for damages under Article 5 of the Protection from Harassment (Northern Ireland) Order 1997. (2) Articles 4 and 6 do not apply to an action to which this Article applies. (3) Subject to Article 50, an action to which this Article applies may not be brought after the expiration of the period specified in paragraphs (4) and (5). (4) Except where paragraph (5) applies, that period is three years from— (a) the date on which the cause of action accrued, or (b) the date of knowledge (if later) of the person injured.
    Limitation (Northern Ireland) Order 1989, art. 47
    (1) For the purposes of this Order, a person is under a disability while— (a) he is an infant; or (b) he is of unsound mind. (2) For the purposes of paragraph (1) a person is of unsound mind if he is a person who, by reason of mental disorder within the meaning of the Mental Health (Northern Ireland) Order 1986, is incapable of managing and administering his property and affairs. (3) Without prejudice to the generality of paragraph (2), a person is to be conclusively presumed for the purposes of that paragraph to be of unsound mind— (a) while he is liable to be detained in hospital for treatment or subject to guardianship under the Mental Health (Northern Ireland) Order 1986; and (b) while he is receiving treatment as an in‐patient in any hospital or private hospital within the meaning of that Order without being liable to be detained thereunder, being treatment which follows without any interval a period during which he was liable to be detained in hospital for treatment or subject to guardianship under that Order.
    Limitation (Northern Ireland) Order 1989, art. 48
    (1) If, on the date when any right of action accrued for which a time limit is fixed by this Order, the person to whom it accrued was under a disability, the action may, subject to paragraphs (2) to (8), be brought at any time before the expiration of six years from the date when the person ceased to be under a disability or died, whichever event first occurred, notwithstanding that the time limit has expired. (2) Paragraph (1) does not affect any case where the right of action first accrued to some person (not under a disability) through whom the person under a disability claims. (3) Where a right of action which has accrued to a person under a disability accrues, on the death of that person while still under a disability, to another person under a disability, no further extension of time may be allowed by reason of the disability of the second person.
    Limitation (Northern Ireland) Order 1989, art. 7
    (5). (4) Except where paragraph (5) applies, that period is three years from— (a) the date on which the cause of action accrued, or (b) the date of knowledge (if later) of the person injured. (5) If the person injured dies before the expiration of the period in paragraph (4), the period as respects the cause of action surviving for the benefit of the estate of the deceased by virtue of section 14 of the Law Reform (Miscellaneous Provisions) Act (Northern Ireland) 1937 is three years from— (a) the date of death; or (b) the date of the personal representative's knowledge, whichever is the later. (6) Subject to paragraph (7), in this Article and in Article 9, references to a person's date of knowledge are references to the date on which he first had knowledge of the following facts— (a) that the injury in question was significant; and (b) that that injury was attributable in whole or in part to the act or omission which is alleged to constitute negligence, nuisance or breach of duty; and (c) the identity of the defendant; and (d) if it is alleged that the act or omission was that of a person other than the defendant, the identity of that person and the additional facts supporting the bringing of an action against the defendant, and knowledge that any acts or omissions did or did not, as a matter of law, involve negligence, nuisance or breach of duty is irrelevant.
    Limitation (Northern Ireland) Order 1989, art. 7
    (8) For the purposes of paragraph (6) an injury is significant if the person whose date of knowledge is in question would reasonably have considered it sufficiently serious to justify his instituting proceedings for damages against a defendant who did not dispute liability and was able to satisfy a judgment. (9) For the purposes of paragraph (6) a person's knowledge includes knowledge which he might reasonably have been expected to acquire— (a) from facts observable or ascertainable by him; or (b) from facts ascertainable by him with the help of medical or other appropriate expert advice which it is reasonable for him to seek, but a person is not to be fixed under this paragraph with knowledge of a fact ascertainable only with the help of expert advice so long as he has taken all reasonable steps to obtain (and, where appropriate, to act on) that advice.
    Limitation (Northern Ireland) Order 1989, art. 48
    (5) Where Article 7 or 9(3) applies to an action, in paragraph (1) for “six years” substitute “ three years ”.
  20. Source 20: Practice Direction No. 4 of 2026 - Practice Direction for Personal Injury and Damage Only Civil Litigation Actions (High Court of Justice in Northern Ireland, King’s Bench Division)Practice direction · Office of the Lady Chief Justice / Judiciary NI (High Court of Justice in Northern Ireland) · Glossary of Terms, PlaintiffPractice Direction No. 4 of 2026, signed 13 October 2026, has effect from 13 October 2026 (decision page: Delivered 13 October 2026; file name "Final (v2) - 060726") · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    NI High Court Practice Direction 4 of 2026 (PI and damage only actions), Glossary of Terms, ‘Plaintiff’
    Plaintiff – A plaintiff is a person who brings a civil action against another person or entity in court.
  21. Source 21: Make a personal injury claimOfficial guidance · Official Injury Claim · Eligibility list under “You can make a claim through Official Injury Claim if”Live page; no version date stated · read on 3 November 2026Open the sourceOur page on this source
    Show the 2 quoted extracts
    “Make a personal injury claim”, eligibility lead-in and first two bullets
    You can make a claim through Official Injury Claim if: you are aged 18 or over the accident happened in England or Wales
    “Make a personal injury claim”, eligibility lead-in and first two bullets
    You can make a claim through Official Injury Claim if: you are aged 18 or over the accident happened in England or Wales
  22. Source 22: The County Court Fees (Amendment) Order (Northern Ireland) 2026Statutory instrument · Department of Justice (Northern Ireland); legislation.gov.uk · Article 1; article 3 and Schedule, substituted Schedule 1, Section I, items 6 and 14, column “As from 01/04/26”Original made text dated 3 March 2026; operative from 1 April 2026 · read on 3 November 2026Official textOur page on this source
    Show the 6 quoted extracts
    Schedule, Section I, current column header
    As from 01/04/26
    Schedule, Section I item 6, lead-in and all three value bands, 1 April 2026 fee column
    6 | On a civil bill, application or notice claiming (whether on foot of a contract or tort or by virtue of any enactment or otherwise) a sum of money or goods or chattels or any combination thereof of a value— not exceeding £1000 | As from 01/04/26 | £244.00 exceeding £1000 but not exceeding £5000 | As from 01/04/26 | £269.00 exceeding £5000 | As from 01/04/26 | £302.00
    Schedule, Section I item 6, lead-in and value band 1, 1 April 2026 fee column
    6 | On a civil bill, application or notice claiming (whether on foot of a contract or tort or by virtue of any enactment or otherwise) a sum of money or goods or chattels or any combination thereof of a value— not exceeding £1000 | As from 01/04/26 | £244.00
    Schedule, Section I item 6, lead-in and value band 2, 1 April 2026 fee column
    6 | On a civil bill, application or notice claiming (whether on foot of a contract or tort or by virtue of any enactment or otherwise) a sum of money or goods or chattels or any combination thereof of a value— exceeding £1000 but not exceeding £5000 | As from 01/04/26 | £269.00
    Schedule, Section I item 6, lead-in and value band 3, 1 April 2026 fee column
    6 | On a civil bill, application or notice claiming (whether on foot of a contract or tort or by virtue of any enactment or otherwise) a sum of money or goods or chattels or any combination thereof of a value— exceeding £5000 | As from 01/04/26 | £302.00
    Schedule, Section I item 14, Certificate of Readiness and 1 April 2026 fee column
    14 | On a Certificate of Readiness | As from 01/04/26 | £407.00
  23. Source 23: Guidance Note - Civil Proceedings in the County CourtOfficial guidance · Judiciary of Northern Ireland; Principal Civil Judge and Presiding District Judge · Paragraphs 1–10; especially paragraphs 6–8, PDF page 3December 2023; official current listing dated 18 December 2023 · read on 3 November 2026Open the sourceOur page on this source
    Show the quoted extract
    Paragraph 8, lead-in and first two list entries, PDF p. 3
    The following documents will only be accepted by the court office in hard copy:- Civil Bills Notices of Intention to Defend
  24. Source 24: Using a SolicitorOfficial guidance · Law Society of Northern Ireland · Discover our Professional Services: Law Society Mediation Service (LSMS) linkLive page; no version date stated · read on 3 November 2026Open the sourceOur page on this source
    Show the quoted extract
    Discover our Professional Services
    Law Society Mediation Service (LSMS)
  25. Source 25: Pre-Action Protocol for Personal Injury ClaimsPre-action protocol · Ministry of Justice · Pre-Action Protocol for Personal Injury Claims, para. 2Updated: Friday, 22 March 2024 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    Pre-Action Protocol for Personal Injury Claims, para. 2
    2.1 The Protocol’s objectives are to— (a) encourage the exchange of early and full information about the dispute; (b) encourage better and earlier pre-action investigation by all parties; (c) enable the parties to avoid litigation by agreeing a settlement of the dispute before proceedings are commenced; (d) support the just, proportionate and efficient management of proceedings where litigation cannot be avoided; and (e) promote the provision of medical or rehabilitation treatment (not just in high value cases) to address the needs of the Claimant at the earliest possible opportunity.
  26. Source 26: Act of Sederunt (Sheriff Court Ordinary Cause Rules) 1993 — Ordinary Cause Rules 1993, Appendix 4: The Personal Injury Pre-Action ProtocolPre-action protocol · Court of Session (Act of Sederunt); published by the Scottish Courts and Tribunals Service · Personal Injury Pre-Action Protocol (Ordinary Cause Rules 1993, Appendix 4), para. 3No version or date stated in the document or on the SCTS page; text as published on 2026-10-31 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    Personal Injury Pre-Action Protocol (Ordinary Cause Rules 1993, Appendix 4), para. 3
    3. The aims of the Protocol are to assist parties to avoid the need for, or mitigate the length and complexity of, civil proceedings by encouraging: • the fair, just and timely settlement of disputes prior to the commencement of proceedings; and • good practice, as regards: – early and full disclosure of information about the dispute; – investigation of the circumstances surrounding the dispute; and – the narrowing of issues to be determined through litigation in cases which do not reach settlement under the Protocol
  27. Source 27: County Court Rules (Northern Ireland) 1981Court rules · legislation.gov.uk (The National Archives); King's Printer · County Court Rules (Northern Ireland) 1981, Order 1981 r. 1Latest revised version on legislation.gov.uk, valid from 2025-11-26; editorially updated 2026-06-05 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    County Court Rules (Northern Ireland) 1981, Order 1981 r. 1
    The notice of proceedings to be given by a claimant to an insurer (or the giver of a security) under Article 98 of the Road Traffic (Northern Ireland) Order 1981 shall be in Form 292, with such variations as the circumstances may require. [ . . .] [ . . .]
  28. Source 28: The Rules of the Court of Judicature (Northern Ireland) (Revision) 1980Court rules · legislation.gov.uk (The National Archives); King's Printer · Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 34 r. 2Latest revised version on legislation.gov.uk, valid from 2025-07-11; editorially updated 2025-08-27 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 34 r. 2
    (1) The plaintiff in any action shall within 6 weeks after the close of pleadings, or within the period fixed by an order of the Court, set down the action for trial. (2) Where the plaintiff fails to set down the action for trial, the defendant may set it down or apply to the Court to dismiss the action for want of prosecution and, on the hearing of any such application, the Court may order the action to be dismissed accordingly or make such order as it thinks fit. [E.r. 2]
  29. Source 29: The Limitation (Northern Ireland) Order 1989Act · legislation.gov.uk (The National Archives); King's Printer · Article 50(1)Latest revised version on legislation.gov.uk, valid from 2026-04-06; editorially updated 2026-05-11 · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    Limitation (Northern Ireland) Order 1989, art. 50
    (1) If it appears to the court that it would be equitable to allow an action to proceed having regard to the degree to which— (a) the provisions of Article 7, 8 or 9 prejudice the plaintiff or any person whom he represents; and (b) any decision of the court under this paragraph would prejudice the defendant or any person whom he represents, the court may direct that those provisions are not to apply to the action, or are not to apply to any specified cause of action to which the action relates.
  30. Source 30: Small claims processOfficial guidance · nidirect (Northern Ireland government website) · nidirect, 'Small claims process': 'Small claims'No date is shown on the page; page metadata (article:modified_time) gives 4 August 2026 · read on 3 November 2026Open the sourceOur page on this source
    Show the quoted extract
    nidirect, 'Small claims process': 'Small claims'
    In general a small claim is one where the value to be claimed is not more than £5,000 and which does not relate to personal injuries, road traffic accidents, libel or slander, title to land, legacy or annuity or any property of a marriage. If the total sum at issue between the same parties exceeds £5,000, the claimant must either: abandon any amount due over £5,000 (this will be expressly noted) issue a civil bill in the County Court for a full hearing (up to £30,000) The Civil Processing Centre, in Laganside Courts, processes all cases at the start but if a case is disputed it is then transferred to the office that is within the original application for hearing. There are two types of small claim: liquidated - where the amount of claim is set, for example, loans or goods and services not paid for unliquidated - where the amount is estimated, for example, damage to property, faulty goods or workmanship Once a case has been submitted to the Civil Processing Centre and verified, the respondent (the person against whom the claim is made) is then posted a small claims pack giving all relevant information about the case, including a copy of the completed small claims application form. The court does not pay the amount that is awarded; it only decides who is liable. A Decree or Order made by the Small Claims Court is a County Court Judgment (CCJ) and may affect a respondent's credit status. It may also affect an applicant’s credit status if a successful counterclaim is made. To find out more information about the small claims application procedure contact the Civil Processing Team at: civilprocessingcentre@courtsni.gov.uk
  31. Source 31: Pre-Action Protocol Personal Injury and Damage Only Road Traffic Accident ClaimsPre-action protocol · Office of the Lady Chief Justice / Judiciary NI (County Court of Northern Ireland) · NI County Court Pre-Action Protocol (PI and damage-only RTA claims), Appendix A (letter of claim)Delivered 06 February 2023, Keegan LCJ (judiciaryni.uk decision page); the protocol text itself states no date · read on 3 November 2026Official textOur page on this source
    Show the quoted extract
    NI County Court Pre-Action Protocol (PI and damage-only RTA claims), Appendix A (letter of claim)
    14. We expect an acknowledgement of this letter within 21 days by yourself or your insurers otherwise proceedings may be issued against you without further notice and costs may be awarded against you.
  32. Source 32: The Court of Judicature Fees (Amendment) Order (Northern Ireland) 2026Statutory instrument · Department of Justice (Northern Ireland); legislation.gov.uk · Article 1; article 3 and Schedule, substituted Section 1, items 1(a) and 7(a), column “As from 01/04/26”Original made text dated 3 March 2026; operative from 1 April 2026 · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    Schedule, Section 1, current column header
    As from 01/04/26
    Schedule, Section 1 item 1 lead-in and limb (a), 1 April 2026 fee column
    1. | On sealing— (a) a writ of summons, or | Fee £ As from 01/04/26 | £326.00
    Schedule, Section 1 item 7 lead-in and limb (a), 1 April 2026 fee column
    7. | On entering or setting down any cause or matter for trial, hearing or further consideration in court, except where it is otherwise provided for in this Schedule (a) without a Jury | Fee £ As from 01/04/26 | £488.00
    Schedule, Section 1 item 7 lead-in and limb (a), 1 April 2026 fee column
    7. | On entering or setting down any cause or matter for trial, hearing or further consideration in court, except where it is otherwise provided for in this Schedule (a) without a Jury | Fee £ As from 01/04/26 | £488.00
  33. Source 33: Customer Service Standards for Key UsersOfficial guidance · Department of Justice (Northern Ireland); Northern Ireland Courts and Tribunals Service · Customer Standards - Civil Processing CentreLive page; no version date stated · read on 3 November 2026Open the sourceOur page on this source
    Show the quoted extract
    Customer Standards - Civil Processing Centre
    We will give advice about the county court administrative processes relating to small claims and civil bills, but not legal advice
  34. Source 34: The County Court Rules (Northern Ireland) 1981Official form · Northern Ireland Courts and Tribunals Service; Department of Justice · Appendix 1, Forms 9 and 10, printed/PDF pages 249–250NICTS compilation updated to 1 February 2021; only unchanged form identification used, checked against live revised rules 3 November 2026 · read on 3 November 2026Open the sourceOur page on this source
    Show the 2 quoted extracts
    Appendix 1, Form 9, printed/PDF page 249
    FORM 9 Ordinary civil bill
    Appendix 1, Form 10, printed/PDF page 250
    FORM 10 Endorsement on ordinary civil bill
  35. Source 35: The Rules of the Court of Judicature (Northern Ireland) (Revision) 1980Court rules · legislation.gov.uk (The National Archives); King's Printer · Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 2; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 3; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 4; Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 5Latest revised version on legislation.gov.uk, valid from 2025-07-11; editorially updated 2025-08-27 · read on 3 November 2026Official textOur page on this source
    Show the 4 quoted extracts
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 2
    (1) Any period of time fixed by these Rules or by any judgment, order or direction for doing any act shall be reckoned in accordance with the following provisions of this rule. (2) Where the act is required to be done within a specified period after or from a specified date, the period begins immediately after that date. (3) Where the act is required to be done within or not less than a specified period before a specified date, the period ends immediately before that date. (4) Where the act is required to be done a specified number of clear days before or after a specified date, at least that number of days must intervene between the day on which the act is done and that date. (5) Where, apart from this pargraph, the period in question, being a period of 7 days or less, would include a Saturday, Sunday or bank holiday, Christmas Day or Good Friday, that day shall be excluded. (6) In paragraph (5) “bank holiday” means a day which is, or is to be observed as, a bank holiday in Northern Ireland under the Banking and Financial Dealings Act 1971. [E.r. 2]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 3
    Unless the Court otherwise directs, the period of the Long Vacation shall be excluded in reckoning any period prescribed by these Rules or by any order or direction for serving, filing or amending any pleading. [E.r. 3]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 4
    Where the time prescribed by these Rules, or by any judgment, order or direction, for doing any act at an office of the Supreme Court expires on a day on which that office is closed, and by reason thereof that act cannot be done on that day, the act shall be in time if done on the next day on which that office is open. [E.r. 4]
    Rules of the Court of Judicature (Northern Ireland) (Revision) 1980, Order 3 r. 5
    (1) The Court may, on such terms as it thinks just, by order extend or abridge the period within which a person is required or authorised by these Rules, or by any judgment, order or direction, to do any act in any proceedings. (2) The Court may extend any such period as is referred to in paragraph (1) although the application for extension is not made until after the expiration of that period. (3) The period, within which a person is required by these Rules, or by any order or direction, to serve, file or amend any pleading or other document may be extended by consent (given in writing) without an order of the Court being made for that purpose. (4) In this rule references to the Court shall be construed as including references to the Court of Appeal. [E.r. 5]
  36. Source 36: Kerr (Ellen) v Ulsterbus LtdJudgment · High Court of Justice in Northern Ireland · [1]–[18], especially [3], [12]–[17]Approved judgment, subject to editorial corrections · read on 3 November 2026[2010] NIQB 2 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 6 January 2010 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 7 quoted extracts
    [1], printed p. 1
    The Plaintiff/Respondent (hereinafter “the Plaintiff”) brought a claim for damages against the Appellant arising out of a road traffic accident. The substantive determination of her claim consisted of a decree for £7,500 in her favour. There is no appeal against this decree.
    [3](d)–(f), printed p. 2
    On 4th February 2008, the Defendant initiated an application to remit the action to the County Court.
    [3](e), printed p. 2
    On 1st May 2008, following a contested hearing, the Master ordered that the action be remitted to the County Court.
    [14], printed p. 6
    Ultimately, I consider the real question to be whether there are grounds upon which this court should interfere with the exercise of the deputy County Court Judge’s discretion, having regard to the deference with which his ruling on the contested costs issue should be treated. I conclude that no such grounds have been made out.
    Kerr [17], two sentences on the remittal costs factor, printed and PDF pp. 7–8
    The final factor which I weigh is that, in the generality of cases where a remitted action results in an award of this order, the Defendant should not be liable for the costs of successful remittal proceedings. Approached in this way, the present case may properly be considered an exception to a general rule.
    [17], printed p. 7
    It follows that this appeal must be dismissed.
    [13], printed p. 6
    I acknowledge that the Appellant achieved partial success, by confining the Plaintiff’s award within the jurisdictional limit of the County Court. However, the event, which features prominently in the general rule as to costs, can scarcely be said to have been fully, or even substantially, successful from the Appellant’s perspective.
  37. Source 37: Monaghan (Richard) v The Very Reverend Graham sued on behalf of the Trustees of Milltown CemeteryJudgment · High Court of Justice in Northern Ireland · [1]–[26], especially [16]–[19], [23]–[26]Approved judgment, subject to editorial corrections · read on 3 November 2026[2013] NIQB 53 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 3 May 2013 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 11 quoted extracts
    [2], printed p. 1
    The plaintiff alleges that on 27 November 2010 he slipped and fell on black ice in Milltown Cemetery sustaining personal injuries.
    [16], printed pp. 5–6
    At a fundamental level the pre-action protocol is an articulation of fairness. Before proceedings are issued the plaintiff should give proper information to allow a view to be formed by the defendant. A similar obligation rests on the defendant.
    [18], printed p. 6
    The defendant’s insurers did not comply with the protocol. No reasons were given for the denial of liability. No documents were made available despite the categories being requested or alternatively being obvious.
    [19], printed p. 6
    Any failure to comply with the pre-action protocol can be taken into account in the exercise of discretion.
    [23], printed p. 8
    I consider that the documents sought by the plaintiff are clearly necessary for the fair disposal of the cause or matter and for saving costs.
    [23], printed p. 8
    I allow the appeal and make an order that the defendant by 12 noon on 29 May 2013 disclose whether the documents set out in paragraph 3 of this judgment are in his possession, custody or power and to produce to the applicant such of those documents as are in his possession, custody or power.
    [24]–[25], printed p. 8
    In this case there has been a clear breach of the pre-action protocol, it has been persisted in, it has been unexplained and I consider that to be fault on the part of the defendant.
    [25], printed p. 8
    I consider it appropriate to order the defendant to pay not only the costs of both this appeal and of the hearing before the Master on an indemnity basis but also the costs of complying with the order.
    [1], printed p. 1
    This is an application by originating summons brought by Richard Monaghan, the plaintiff, for pre-action discovery pursuant to Section 31 of the Administration of Justice Act 1970 and Order 24 Rules 8 and 9 of the Rules of the Court of Judicature (Northern Ireland) 1980. The application was heard by Master Bell who declined to make an Order and the plaintiff has appealed to this court.
    [4], printed p. 2
    The defendants contend, and the Master held, that the documents are not necessary at this stage for disposing fairly of the cause or matter or for saving costs.
    [21], printed p. 7
    There are differences between the position in Northern Ireland and the position in England and Wales. For instance the Civil Procedure Rules use the word “desirable” rather than “necessary.”
  38. Source 38: Kerr (Ann) v Conor Toal; Declan Gordon v Vera Best and Iain Best; Margaret Gregory v Olivia Cashel O’Farrell; John Chadwick v Pawel KaczorJudgment · High Court of Justice in Northern Ireland · [1]–[44], especially [6], [11]–[16], [27]–[28], [34], [39], [43]–[44]Approved judgment, subject to editorial corrections · read on 3 November 2026[2015] NIQB 83 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 12 February 2015 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 11 quoted extracts
    [1]–[2], printed p. 2
    This ruling addresses a number of issues in four separate appeals arising in damage only cases in respect of claims for the hire of replacement vehicles under credit hire agreements from Crash Services.
    [6], printed p. 3
    Inevitably there will be a degree of facts specificity which would prevent this court laying down overarching procedures and approaches for every case, and the court is also mindful that it is neither a rule making body, nor am I empowered to issue Practice Directions.
    [13](c), printed p. 7
    I see nothing onerous or difficult in being able to say at the outset or at some point before proceedings if impecuniosity is being raised and the basis for it being raised.
    [15]–[16], printed p. 7
    In general terms if both parties genuinely embrace the concept of speed and cost saving, then in the opening letter as much information should be given in relation to car hire and the issue of impecuniosity, if raised, and if not then available, as quickly thereafter as possible.
    [27], printed p. 11
    The purpose of the Certificate is to notify the office that the plaintiff is ready to proceed in the matter, and that to the best of his or her knowledge and belief there are no interlocutory matters outstanding.
    [28](b), printed p. 11
    If the answer to (a) is “no” then no further interrogatories require to be answered.
    [39], printed p. 14
    The order of the court therefore is that the application for replies is refused. Costs will be award to the plaintiff/respondent.
    [44], printed pp. 15–16
    The court reiterates its view that over and above the rights of parties afforded to them under the Rules of Court every effort should be made to achieve an early agreement when dealing with commercial matters such as car hire and damage to property. To achieve that end there has to be a free flow of information and a practical engagement between all parties.
    [28](a), printed p. 11
    That within seven days of the date of this Order the plaintiff’s solicitors should advise the defendant’s solicitors as to whether or not the plaintiff claims impecuniosity as the reason for him entering into the credit sale agreement with Crash Services:
    [34](a)–(b), printed p. 13
    Within seven days of the date of this order the plaintiff’s solicitors will advise the defendant’s solicitors if the plaintiff intends to rely on his impecuniosity in relation to entering into the credit hire agreement:
    [43], printed p. 15
    For the same reasons I have given in that case the order in respect of this case will be that set out at paragraph [34].
  39. Source 39: Quinn (Miceal William) and Quinn (William Kevin) v McAleenan (Kevin) and McConville (Michael)Judgment · High Court of Justice in Northern Ireland · [1]–[22], especially first [2] under “The conduct of this appeal”, [3]–[4], [21]–[22]Approved judgment, subject to editorial corrections · read on 3 November 2026[2010] NIQB 31 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 3 March 2010 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 5 quoted extracts
    [2] (The conduct of this appeal), printed pp. 1–2
    In this appeal I have followed the same course adopted by McCloskey J in an unreported decision Kerr v Ulsterbus Limited [2010] NIQB 2 delivered 6 January 2010 when, bearing in mind the overriding objective enshrined in Order 1, Rule 1A of the Rules of the Court of Judicature of Northern Ireland, the mode of hearing agreed by the parties was that the appeal would be decided exclusively on the basis of written submissions.
    [3]–[4] (Background to the application), printed p. 2
    Civil bills were issued by the plaintiffs on 16 September 2008 seeking £15,000 damages for personal injuries, loss and damage sustained by them by reason of the assault, battery and trespass to the person of the plaintiffs by the servants or agents of the defendants.
    [4] (Background to the application), printed p. 2
    No Notice of Intention to defend these cases was lodged.
    [21], printed p. 6
    Having considered all these matters however, I find no basis for finding a merits defence in this instance.
    [22], printed pp. 6–7
    In all the circumstances I find no basis for upsetting the discretion exercised by the District Judge in these cases. I have come to precisely the same conclusion having reviewed the material before me. I therefore dismiss these appeals and award costs against the appellants.
  40. Source 40: John Donnelly Developments Limited v Niall Curran and Patricia CurranJudgment · High Court of Justice in Northern Ireland · [1]–[10], especially [2], [5]–[8], [10]Approved judgment, subject to editorial corrections · read on 3 November 2026[2013] NIQB 66 · High Court of Justice in Northern Ireland, Queen’s Bench Division (Commercial Action) · Northern Ireland · 29 May 2013 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 5 quoted extracts
    [5], printed p. 2
    I have given two decisions recently in relation to Pre-action Protocols. The first is Lunney and Danlor Utilities Limited v McGiven [2013] NIQB 49 and the second is Monaghan v The Very Reverend Graham sued on behalf of the Trustees of Milltown Cemetery [2013] NIQB 53. Both of those decisions emphasise the requirement, essentially of fairness, that litigants should be informed as to the issues at the earliest stage.
    [1], printed p. 1
    In this action the plaintiff claims the balance of the contract sum allegedly due from the defendants on foot of a building contract. It is a commercial action. That is so quite irrespective of the contents of the defence and counterclaim in which the defendants allege defective building works.
    [2], printed p. 2
    In the event, it has not been necessary for me to decide that question as I have received an assurance that none of the wasted costs involved in what has proved to be an abortive trial will be borne by either of the litigants in this case.
    [6], printed p. 3
    The Pre-action Protocol did not apply to this action which was commenced some years ago. The parties relied on the pleadings to bring definition to the issues. The defence and counterclaim failed to do so and accordingly at the end of half a day’s hearing the defendants applied to amend the defence and counterclaim.
    [10], printed p. 4
    I give leave to amend and take the case out of the list on the basis of an assurance that the individual litigants will not have to bear any of the costs thrown away.
  41. Source 41: South Eastern Health and Social Care Trust v Colin Flannagan and Capper Trading LimitedJudgment · High Court of Justice in Northern Ireland · [1]–[26], especially [11]–[12], [24]–[26]Approved judgment, subject to editorial corrections · read on 3 November 2026[2015] NIQB 30 · High Court of Justice in Northern Ireland, Queen’s Bench Division · Northern Ireland · 15 April 2015 · Appeal status not confirmed · Our case summaryRead the judgmentOur page on this source
    Show the 7 quoted extracts
    [11], printed p. 4
    In Kerr v Toal (BUR9528) Burgess J referred to the obligation falling on all parties to provide speedy and cost effective systems and to the need to have a proper exchange of information in order to allow proper and reasonable attempts to be made by both parties to resolve issues without the necessity of engaging in the court system.
    [1], printed p. 1
    This is an appeal by the defendants in a credit hire case in which the plaintiff secured an award in the County Court of £4,734.06 together with costs.
    [2], printed p. 1
    The plaintiff’s claim arises out of a road traffic collision which occurred on 4 March 2014 in respect of which the defendants have admitted liability.
    [12], printed p. 5
    There was no evidence as to the financial position of the Department. The plaintiff has not attempted to discharge the burden of proving impecuniosity in respect of the Department. Accordingly the issue of impecuniosity is decided on that ground alone in favour of the defendants.
    [24]–[25], printed p. 10
    I find that the defendant has discharged the onus of establishing that the plaintiff has failed to mitigate its loss by failing to hire at the basic hire rate.
    [25], printed p. 10
    I allow the defendant’s appeal reducing the award by £704.02 so that the ultimate award is £4,030.04.
    [26], printed p. 10
    I will hear counsel in relation to the issue of costs and any other ancillary orders.
This guide is general information, not legal advice. For advice on your own situation, see Getting help: free advice and how to find a solicitor.

Spotted a mistake? Report a mistake in this guide.

Source
All sources

    Install on iPhone or iPad

    1. Tap the Share button in Safari (the square with an upward arrow).
    2. Choose Add to Home Screen.
    3. Tap Add. The app appears next to your other apps.

    The first steps after a collision, the checklists and the glossary stay available without signal.