HOW LONG
As soon as possible and no later than 20 working days after receiving the written representations. [47]
Deadlines depend on the facts. This is a summary from the guides, not a calculation for your case. Check the guide below for the details and exceptions, and get advice quickly if a time limit may be close.
What starts the clock
The Scottish public authority receives your qualifying written review representations. [47]
How it is calculated
If the deadline is missed
Exceptions and limits
Which period this covers
Scottish EIR regulation 16(3)–(5) as currently in force. [47]
Read the full guide
How do I claim for pothole or road-defect damage in Scotland?GuideGuides that use this deadline
Each guide explains the deadline for its own situation, sometimes under a different name.
Sources
The numbers match the sources of the guide that explains this deadline.
[45] The Environmental Information (Scotland) Regulations 2004 · regs. 5(1)–(2) and 7(1)–(3)
(1) Subject to paragraph (2), a Scottish public authority that holds environmental information shall make it available when requested to do so by any applicant. (2) The duty under paragraph (1)– (a) shall be complied with as soon as possible and in any event no later than 20 working days after the date of receipt of the request; and (b) is subject to regulations 6 to 12.
(1) The period of 20 working days referred to in– (a) regulation 5(2)(a); (b) regulation 6(2)(a); and (c) regulation 13(a), may be extended by a Scottish public authority by a further period of up to 20 working days if the volume and complexity of the information requested makes it impracticable for the authority either to comply with the request within the earlier period or to make a decision to refuse to do so. (2) Where paragraph (1) applies the Scottish public authority shall notify the applicant accordingly as soon as possible and in any event no later than 20 working days after the date of receipt of the request for the information. (3) Notification under paragraph (2) shall– (a) be in writing; (b) give the authority’s reasons for considering the information to be voluminous and complex; and (c) inform the applicant of the review provisions under regulation 16 and of the enforcement and appeal provisions available in accordance with regulation 17.
About this sourceOfficial text[47] The Environmental Information (Scotland) Regulations 2004 · reg. 16(1)–(5)
(1) Subject to paragraph (2), an applicant may make representations to a Scottish public authority if it appears to the applicant that the authority has not complied with any requirement of these Regulations in relation to the applicant’s request. (2) Representations under paragraph (1) shall be made in writing to the Scottish public authority no later than 40 working days after either the date that the applicant receives any decision or notification which the applicant believes does not comply with these Regulations or the date by which such a decision or notification should have been made, or any other action should have been taken, by the authority but was not made or taken.
(3) The Scottish public authority shall on receipt of such representations– (a) consider them and any supporting evidence produced by the applicant; and (b) review the matter and decide whether it has complied with these Regulations. (4) The Scottish public authority shall as soon as possible and no later than 20 working days after the date of receipt of the representations notify the applicant of its decision. (5) Where the Scottish public authority decides that it has not complied with its duty under these Regulations, it shall immediately take steps to remedy the breach of duty.
About this sourceOfficial text[48] The Environmental Information (Scotland) Regulations 2004 · reg. 2(1), definition of “working day”
“working day” has the same meaning as in section 73 of the Act.
About this sourceOfficial text[49] Freedom of Information (Scotland) Act 2002 · s. 73(1), definition of “working day”
“working day” means any day other than a Saturday, a Sunday, Christmas Day or a day which, under the Banking and Financial Dealings Act 1971 (c.80), is a bank holiday in Scotland.
About this sourceOfficial text[51] Appeal to the Commissioner · Introductory text before “How to make an appeal”
If you're still unhappy after the review stage, you can appeal to the Commissioner.
You can appeal to the Commissioner if: You are unhappy with the outcome of an authority's review The authority refuses to review its decision because it says your request is "vexatious" or "repeated". For an explanation of what this means, see our guidance on why your request might be refused The authority has not responded to your request for review
About this sourceOfficial text
General information, not legal advice. Deadlines depend on the facts; always check the guide and the official sources.