Environmental information: ask the authority for a review

APPLIES IN
Scotland
USED IN
1 guide
EXPLAINED IN
How do I claim for pothole or road-defect damage in Scotland?

HOW LONG

No later than 40 working days after the applicable trigger. [47]

Deadlines depend on the facts. This is a summary from the guides, not a calculation for your case. Check the guide below for the details and exceptions, and get advice quickly if a time limit may be close.

What starts the clock

You receive a decision or notice you believe is deficient, or the date the authority should have decided, notified you or otherwise acted but did not. [47]

How it is calculated

Make written representations to the Scottish public authority. Count working days after the trigger; exclude weekends, Christmas Day and Scottish bank holidays. [47] [48] [49]

If the deadline is missed

A late request is outside the prescribed internal review period. Check the Commissioner’s appeal guidance after an unsatisfactory or missing review. [47] [51]

Exceptions and limits

  • Use the date when the authority should have acted after applying any valid regulation 7 extension, regulation 8 advance-fee pause or regulation 9 further-particulars rule to the initial response period. [45] [83] [47]

Which period this covers

Scottish EIR regulation 16 as currently in force. This is a request-handling clock. [47]

Read the full guide

How do I claim for pothole or road-defect damage in Scotland?Guide

Guides that use this deadline

Each guide explains the deadline for its own situation, sometimes under a different name.

How do I claim for pothole or road-defect damage in Scotland?Guide · Main guideCalled there: Environmental information: ask the authority for a review

Sources

The numbers match the sources of the guide that explains this deadline.

  1. [45] The Environmental Information (Scotland) Regulations 2004 · regs. 5(1)–(2) and 7(1)–(3)

    (1) Subject to paragraph (2), a Scottish public authority that holds environmental information shall make it available when requested to do so by any applicant. (2) The duty under paragraph (1)– (a) shall be complied with as soon as possible and in any event no later than 20 working days after the date of receipt of the request; and (b) is subject to regulations 6 to 12.
    (1) The period of 20 working days referred to in– (a) regulation 5(2)(a); (b) regulation 6(2)(a); and (c) regulation 13(a), may be extended by a Scottish public authority by a further period of up to 20 working days if the volume and complexity of the information requested makes it impracticable for the authority either to comply with the request within the earlier period or to make a decision to refuse to do so. (2) Where paragraph (1) applies the Scottish public authority shall notify the applicant accordingly as soon as possible and in any event no later than 20 working days after the date of receipt of the request for the information. (3) Notification under paragraph (2) shall– (a) be in writing; (b) give the authority’s reasons for considering the information to be voluminous and complex; and (c) inform the applicant of the review provisions under regulation 16 and of the enforcement and appeal provisions available in accordance with regulation 17.
    About this sourceOfficial text
  2. [47] The Environmental Information (Scotland) Regulations 2004 · reg. 16(1)–(5)

    (1) Subject to paragraph (2), an applicant may make representations to a Scottish public authority if it appears to the applicant that the authority has not complied with any requirement of these Regulations in relation to the applicant’s request. (2) Representations under paragraph (1) shall be made in writing to the Scottish public authority no later than 40 working days after either the date that the applicant receives any decision or notification which the applicant believes does not comply with these Regulations or the date by which such a decision or notification should have been made, or any other action should have been taken, by the authority but was not made or taken.
    (3) The Scottish public authority shall on receipt of such representations– (a) consider them and any supporting evidence produced by the applicant; and (b) review the matter and decide whether it has complied with these Regulations. (4) The Scottish public authority shall as soon as possible and no later than 20 working days after the date of receipt of the representations notify the applicant of its decision. (5) Where the Scottish public authority decides that it has not complied with its duty under these Regulations, it shall immediately take steps to remedy the breach of duty.
    About this sourceOfficial text
  3. [48] The Environmental Information (Scotland) Regulations 2004 · reg. 2(1), definition of “working day”

    “working day” has the same meaning as in section 73 of the Act.
    About this sourceOfficial text
  4. [49] Freedom of Information (Scotland) Act 2002 · s. 73(1), definition of “working day”

    “working day” means any day other than a Saturday, a Sunday, Christmas Day or a day which, under the Banking and Financial Dealings Act 1971 (c.80), is a bank holiday in Scotland.
    About this sourceOfficial text
  5. [51] Appeal to the Commissioner · Introductory text before “How to make an appeal”

    If you're still unhappy after the review stage, you can appeal to the Commissioner.
    You can appeal to the Commissioner if: You are unhappy with the outcome of an authority's review The authority refuses to review its decision because it says your request is "vexatious" or "repeated". For an explanation of what this means, see our guidance on why your request might be refused The authority has not responded to your request for review
    About this sourceOfficial text
  6. [83] The Environmental Information (Scotland) Regulations 2004 · regs. 8(4)–(7), 9(2) and (4)

    (4) A Scottish public authority may require that payment of the whole or part of a fee under paragraph (1) be made in advance of making information available. (5) Where a Scottish public authority imposes a requirement under paragraph (4) it shall notify the applicant in writing. (6) Where a Scottish public authority has notified an applicant that advance payment is required under paragraph (5) then that authority is not obliged to– (a) make the information requested available under regulation 5(1); or (b) comply with regulations 6, 7 or 13, unless the fee is paid; and any such fee must be paid within a period of 60 working days beginning with the day on which the authority gave such notification. (7) No working day from and including the day on which notice under paragraph (5) is given up to and including the day on which a fee is paid shall count for the purposes of determining any period of working days in accordance with regulations 5(2)(a), 6(2)(a) and 13(a).
    (2) Where a request has been formulated in too general a manner, the authority shall– (a) ask the applicant as soon as possible, and in any event no later than 20 working days after the date of receipt of request, to provide more particulars in relation to the request; and (b) assist the applicant in providing those particulars.
    (4) In any case to which paragraph (2) applies, the date on which the further particulars are received by the authority shall be treated as the date of the request for the purposes of regulations 5(2)(a), 6(2)(a) and 13(a) and any period within which the authority is required to respond to that request by these Regulations shall begin on the day following that date.
    About this sourceOfficial text

General information, not legal advice. Deadlines depend on the facts; always check the guide and the official sources.

Install on iPhone or iPad

  1. Tap the Share button in Safari (the square with an upward arrow).
  2. Choose Add to Home Screen.
  3. Tap Add. The app appears next to your other apps.

The first steps after a collision, the checklists and the glossary stay available without signal.