HOW LONG
Normally 28 days from the applicable statutory date, after available arbitral review/correction routes are exhausted. [58]
Deadlines depend on the facts. This is a summary from the guides, not a calculation for your case. Check the guide below for the details and exceptions, and get advice quickly if a time limit may be close.
What starts the clock
Under revised section 70(3A): the award date, notification of arbitral appeal/review result, or the specified material correction/additional-award/application decision date. [58]
How it is calculated
A party must bring the court application under the appropriate Arbitration Act provision. A correction or application affects the trigger only on the materiality terms in section 70(3A)–(3B). Obtain immediate advice on calculation and procedure. [58]
If the deadline is missed
A late or procedurally barred challenge may fail; use the correct court route immediately rather than waiting for a service complaint. [58]
Exceptions and limits
Which period this covers
Read the full guide
How do I claim from the MIB after an accident in Northern Ireland?GuideGuides that use this deadline
Each guide explains the deadline for its own situation, sometimes under a different name.
Sources
The numbers match the sources of the guide that explains this deadline.
[56] Arbitration Act 1996 · s.67(1)
(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court— (a) challenging any award of the arbitral tribunal as to its substantive jurisdiction; or (b) challenging an award made by the tribunal on the merits because the tribunal did not have substantive jurisdiction. A party may lose the right to object (see section 73) and the right to apply is subject to the restrictions in section 70(2) and (3).
About this sourceOfficial text[57] Arbitration Act 1996 · s.68(1)–(2) opening
(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award. A party may lose the right to object (see section 73) and the right to apply is subject to the restrictions in section 70(2) and (3). (2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant—
About this sourceOfficial text[58] Arbitration Act 1996 · s.70(2)–(3B)
(2) An application or appeal may not be brought if the applicant or appellant has not first exhausted— (a) any available arbitral process of appeal or review, and (b) any available recourse under section 57 (correction of award or additional award). (3) Any application or appeal must be brought within 28 days of the applicable date. (3A) In subsection (3), “the applicable date” means— (a) in a case where there has been any arbitral process of appeal or review, the date when the applicant or appellant was notified of the result of that process; (b) in a case where the tribunal has, under section 57, made a material correction to an award or has made a material additional award, the date of the correction or additional award; (c) in a case where a material application for a correction to an award or for an additional award has been made to the tribunal under section 57 and the tribunal has decided not to grant the application, the date when the applicant or appellant was notified of that decision; (d) in any other case, the date of the award. (3B) For the purposes of subsection (3A)— (a) a correction to an award, (b) an additional award, or (c) an application under section 57, is “material” if any matter to which it relates is material to the application or appeal under section 67, 68 or 69.
About this sourceOfficial text[61] Arbitration Act 2025 · s.17(4)
Subject to any transitional or saving provision made under subsection (3), an amendment made by sections 1 to 14— (a) does not apply to— (i) arbitral proceedings commenced before the day on which the section making the amendment comes into force (“pre-commencement arbitral proceedings”), (ii) court proceedings (whenever commenced) in connection with pre-commencement arbitral proceedings or an award made in pre-commencement arbitral proceedings, or (iii) any other court proceedings commenced before the day on which the section making the amendment comes into force; (b) otherwise applies in relation to an arbitration agreement whenever made.
About this sourceOfficial text[62] The Arbitration Act 2025 (Commencement) Regulations 2025 · reg.2
The Arbitration Act 2025 comes into force on 1st August 2025 to the extent that it is not already in force.
About this sourceOfficial text
General information, not legal advice. Deadlines depend on the facts; always check the guide and the official sources.