HOW LONG
Deadlines depend on the facts. This is a summary from the guides, not a calculation for your case. Check the guide below for the details and exceptions, and get advice quickly if a time limit may be close.
What starts the clock
The compensator agrees to make an interim payment under paragraph 9.5. [51]
How it is calculated
If the deadline is missed
Exceptions and limits
The 30-business-day provision applies if no recoverable-benefits certificate is held, or it will not remain in force for at least 10 business days. The compensator must apply as soon as possible and notify the claimant. Property-related damages do not require waiting for that certificate. [51]
Agreed liability apportionment and recoverable benefits can affect payment. Specific items paid in full are satisfied; general payments are credited at conclusion and may be ordered repaid. [51]
Which period this covers
Read the full guide
How can I get rehabilitation after a crash, and who pays for it?GuideGuides that use this deadline
Each guide explains the deadline for its own situation, sometimes under a different name.
Sources
The numbers match the sources of the guide that explains this deadline.
[24] Private patients: terms and conditions · Payment and Charges — You should read this section if your treatment is covered by private medical insurance
You will, however, remain ultimately responsible for paying any charges relating to our treatment and care of you.
About this sourceOfficial text[40] Pre-Action Protocol for Personal Injury Claims below the Small Claims Limit in Road Traffic Accidents (“The RTA Small Claims Protocol”) · Paragraphs 4.2–4.4
When to use this Protocol 4.2 This Protocol applies to any claim where all of the following conditions apply— (1) the claim arises from a road traffic accident which occurred in England or Wales on or after31 May 2021; (2) the claim includes a claim for damages for injury; and (3) the claimant values the overall claim at no more than £10,000 and the claim for damages for injury at no more than £5,000, save that the value of any non-protocol vehicle costs is excluded for the purposes of valuing the claim in this Protocol. 4.3 Even if all of the conditions in paragraph 4.2 do apply, this Protocol does not apply to a claim— (a) in respect of a breach of duty owed to a road user by a person who is not a road user; (b) where the injuries which are claimed for were at least partly caused by a breach by the defendant of one or more of the relevant provisions as defined by section 53 of the Health and Safety at Work etc Act 1974; (c) to the MIB pursuant to the Untraced Drivers’ Agreement 2017 or any subsequent or supplementary Untraced Drivers’ Agreements (this agreement applies where a claim involves an accident with a driver who has not been identified – also known as a “hit and run” – this Protocol should not be used when making such a claim); (d) where at the time the accident occurred, the claimant was a vulnerable road user; (e) where the claimant or defendant acts as a personal representative of a deceased person; (f) where on the date the claim is started, the claimant is a child; (g) where the claimant or defendant is a protected party as defined in rule 21.1(2); (h) where the claimant is bankrupt; or (i) where the defendant’s vehicle is registered outside the United Kingdom. 4.4 If the claimant uses this Protocol where any of the circumstances in paragraph 4.3 apply, the claim will not be accepted, and the claimant will be notified of the reason for non-acceptance through the Portal. The claimant should also consider seeking advice in these circumstances.
About this sourceOfficial text[50] Pre-Action Protocol for Personal Injury Claims below the Small Claims Limit in Road Traffic Accidents (“The RTA Small Claims Protocol”) · Paragraphs 1.4(1)–(2), 9.3(3) and 9.4(1)
1.4 (1) In this Protocol— (a) a reference to a fixed number of days is a reference to “business days”; (b) “business day” means any day, except Saturday, Sunday, a bank holiday, Good Friday or Christmas Day; and (c) “bank holiday”means a bank holiday in England and Wales. (2) Where a party must respond within a fixed number of days, the time for responding starts on the first business day after the information was sent to that party.
(a) The claimant may only make one interim payment request at any time, but may update an existing request to include additional items either before or after the compensator has responded to the request or the time for response has passed. (b) Where the claimant updates an interim payment request, paragraphs 9.4 to 9.6 apply to the updated request and no longer apply to the original request.
9.4 (1) The compensator must respond to any interim payment request within15 days.
About this sourceOfficial text[51] Pre-Action Protocol for Personal Injury Claims below the Small Claims Limit in Road Traffic Accidents (“The RTA Small Claims Protocol”) · Paragraphs 1.4(1), 9.4(3)–(9) and 9.5
9.5 (1) Unless paragraph (2) applies, where the compensator has agreed to make an interim payment, this must be paid within 10 days of the date of such agreement. (2) Where the compensator agrees to make an interim payment, but does not yet have a certificate of recoverable benefits (which is defined in paragraph 10.10(1)(b)) or does not have one that will remain in force for at least 10 days, the compensator must— (a) apply for a certificate of recoverable benefits as soon as possible; (b) notify the claimant that they have done so; and (c) make the interim payment no more than 30 days from the date of agreement. (3) Other protocol damages can include items caused by the claimant’s injury and other items such as protocol vehicle costs or other damage to property. In this Protocol, these are called other damages – injury related and other damages – property. Where the interim payment is for items that are other damages – property, the compensator does not need to wait for a certificate of recoverable benefits before making a payment in accordance with paragraph (1).
(3) Where the interim payment is stated to cover specific items in full, those items are regarded as satisfied and are then removed from the claim. The court cannot order such an interim payment to be repaid. (4) An interim payment intended to cover specific items can only be made for the sums as claimed in full. Any payment agreed or awarded for less than the sum claimed for that item will be treated as a general interim payment under paragraph (5) below. (5) Where a general interim payment is made, the claim remains as stated and the payment will be taken into account at the conclusion of the claim, to be offset, first, against other protocol damages. The court can order a general interim payment to be repaid, see paragraph (7) below.
(8) An agreement under paragraph 6.8 in which the claimant accepts any proposal for a percentage of liability in part means that any interim payment will have to be reduced to take this percentage into account. (9) When making an interim payment the compensator must deduct any recoverable benefits from relevant damages. An explanation of the benefits position is at paragraphs 10.10 and 10.11.
About this sourceOfficial text
General information, not legal advice. Deadlines depend on the facts; always check the guide and the official sources.