Authority response to a Freedom of Information Act request

APPLIES IN
England and Wales
USED IN
1 guide
EXPLAINED IN
How can I challenge a rejected pothole claim in England or Wales?

HOW LONG

Promptly and normally by the twentieth working day following receipt. [22]

Deadlines depend on the facts. This is a summary from the guides, not a calculation for your case. Check the guide below for the details and exceptions, and get advice quickly if a time limit may be close.

What starts the clock

Receipt of your valid request or, where applicable, later receipt of reasonable further details needed to identify and locate the information. [21] [22]

How it is calculated

Count working days following the date of receipt. Exclude Saturdays, Sundays, Christmas Day, Good Friday and statutory bank holidays in any part of the UK. [22]

If the deadline is missed

Ask for internal review where available. If the issue remains unresolved, use the ICO’s FOI route. [23] [89]

Exceptions and limits

  • Exclude the relevant fee notice to payment period if the fee is paid as required. A qualified public-interest decision may take a reasonable extra time and regulations can vary time in particular cases. The initial refusal notice still has its own timing. [22]

  • Environmental records are dealt with under the EIR and have a different extension test. [21] [16]

Which period this covers

Section 10 as checked on 6 November 2026. The clock turns on the information request and its statutory receipt date. [22]

Read the full guide

How can I challenge a rejected pothole claim in England or Wales?Guide

Guides that use this deadline

Each guide explains the deadline for its own situation, sometimes under a different name.

How can I challenge a rejected pothole claim in England or Wales?Guide · Main guideCalled there: Authority response to a Freedom of Information Act request

Sources

The numbers match the sources of the guide that explains this deadline.

  1. [16] The Environmental Information Regulations 2004 · regs. 2(1) (“working day”), 5(1)–(3) and 7(1)–(3)

    (1) Subject to paragraph (3) and in accordance with paragraphs (2), (4), (5) and (6) and the remaining provisions of this Part and Part 3 of these Regulations, a public authority that holds environmental information shall make it available on request. (2) Information shall be made available under paragraph (1) as soon as possible and no later than 20 working days after the date of receipt of the request. (3) To the extent that the information requested includes personal data of which the applicant is the data subject, paragraph (1) shall not apply to those personal data.
    “working day” has the same meaning as in section 10(6) of the Act.
    (1) Where a request is made under regulation 5, the public authority may extend the period of 20 working days referred to in the provisions in paragraph (2) to 40 working days if it reasonably believes that the complexity and volume of the information requested means that it is impracticable either to comply with the request within the earlier period or to make a decision to refuse to do so. (2) The provisions referred to in paragraph (1) are— (a) regulation 5(2); (b) regulation 6(2)(a); and (c) regulation 14(2). (3) Where paragraph (1) applies the public authority shall notify the applicant accordingly as soon as possible and no later than 20 working days after the date of receipt of the request.
    About this sourceOfficial text
  2. [21] Freedom of Information Act 2000 · ss. 1(1)–(4), 8(1)–(2) and 39(1)

    (1) Any person making a request for information to a public authority is entitled— (a) to be informed in writing by the public authority whether it holds information of the description specified in the request, and (b) if that is the case, to have that information communicated to him. (2) Subsection (1) has effect subject to the following provisions of this section and to the provisions of sections 2, 9, 12 and 14. (3) Where a public authority— (a) reasonably requires further information in order to identify and locate the information requested, and (b) has informed the applicant of that requirement, the authority is not obliged to comply with subsection (1) unless it is supplied with that further information. (4) The information— (a) in respect of which the applicant is to be informed under subsection (1)(a), or (b) which is to be communicated under subsection (1)(b), is the information in question held at the time when the request is received, except that account may be taken of any amendment or deletion made between that time and the time when the information is to be communicated under subsection (1)(b), being an amendment or deletion that would have been made regardless of the receipt of the request.
    (1) In this Act any reference to a “request for information” is a reference to such a request which— (a) is in writing, (b) states the name of the applicant and an address for correspondence, and (c) describes the information requested. (2) For the purposes of subsection (1)(a), a request is to be treated as made in writing where the text of the request— (a) is transmitted by electronic means, (b) is received in legible form, and (c) is capable of being used for subsequent reference.
    (1) Information is exempt information if the public authority holding it— (a) is obliged by environmental information regulations to make the information available to the public in accordance with the regulations, or (b) would be so obliged but for any exemption contained in the regulations.
    About this sourceOfficial text
  3. [22] Freedom of Information Act 2000 · s. 10(1)–(6)

    (1) Subject to subsections (2) and (3), a public authority must comply with section 1(1) promptly and in any event not later than the twentieth working day following the date of receipt. (2) Where the authority has given a fees notice to the applicant and the fee is paid in accordance with section 9(2), the working days in the period beginning with the day on which the fees notice is given to the applicant and ending with the day on which the fee is received by the authority are to be disregarded in calculating for the purposes of subsection (1) the twentieth working day following the date of receipt. (3) If, and to the extent that— (a) section 1(1)(a) would not apply if the condition in section 2(1)(b) were satisfied, or (b) section 1(1)(b) would not apply if the condition in section 2(2)(b) were satisfied, the public authority need not comply with section 1(1)(a) or (b) until such time as is reasonable in the circumstances; but this subsection does not affect the time by which any notice under section 17(1) must be given.
    (4) The Minister for the Cabinet Office may by regulations provide that subsections (1) and (2) are to have effect as if any reference to the twentieth working day following the date of receipt were a reference to such other day, not later than the sixtieth working day following the date of receipt, as may be specified in, or determined in accordance with, the regulations. (5) Regulations under subsection (4) may— (a) prescribe different days in relation to different cases, and (b) confer a discretion on the Commission.
    (6) In this section— “the date of receipt” means— the day on which the public authority receives the request for information, or if later, the day on which it receives the information referred to in section 1(3); “working day” means any day other than a Saturday, a Sunday, Christmas Day, Good Friday or a day which is a bank holiday under the Banking and Financial Dealings Act 1971 in any part of the United Kingdom.
    About this sourceOfficial text
  4. [23] Freedom of Information Act 2000 · s. 50(1)–(2)

    (1) Any person (in this section referred to as “the complainant”) may apply to the Commission for a decision whether, in any specified respect, a request for information made by the complainant to a public authority has been dealt with in accordance with the requirements of Part I. (2) On receiving an application under this section, the Commission shall make a decision unless it appears to the Commission— (a) that the complainant has not exhausted any complaints procedure which is provided by the public authority in conformity with the code of practice under section 45, (b) that there has been undue delay in making the application, (c) that the application is frivolous or vexatious, or (d) that the application has been withdrawn or abandoned.
    About this sourceOfficial text
  5. [89] FOI and EIR complaints · “FOI and EIR complaints”, before “Start now”

    Check if your complaint is eligible to come to the ICO or find out if there is more action you need to take before you can complain to us. For example, you may need to have requested an internal review before you can make a complaint.
    About this sourceOfficial text

General information, not legal advice. Deadlines depend on the facts; always check the guide and the official sources.

Install on iPhone or iPad

  1. Tap the Share button in Safari (the square with an upward arrow).
  2. Choose Add to Home Screen.
  3. Tap Add. The app appears next to your other apps.

The first steps after a collision, the checklists and the glossary stay available without signal.