THE LEGAL QUESTION
Whether the agreements suspended unexpired time or merely extended the limitation deadline to the end date, whether later agreements lost earlier protection, and whether protection reached a company not apparently party to the agreement.
The facts
Homeowners brought professional negligence claims about quantity surveying and project management in a building project. Three successive standstill agreements plus side letters led to a final period ending 30 November 2016. Proceedings commenced 1 December 2016 and defendants sought partial strike out on limitation. [59]
What the court decided
The agreements suspended time, challenged claims against the contracting defendants were not barred, and earlier suspension protection was retained. The court did not strike out all claims against the second defendant at that stage, leaving factual identity uncertainty for disclosure. [59]
Why: the reasoning
The operative language and the agreement as a whole controlled. Suspension preserved the same remaining time at the end as at the start. Operative terms prevailed over inconsistent recital language. Particular wording determines effect; earlier decisions disclose no universal rule that every standstill suspends limitation. [59]
Why it matters and its limits
Distinguishes statutory time, procedural service protection and the effect of actual written terms.
WHAT IT DOES NOT DECIDE
Construction dispute used only to illustrate contractual interpretation. Do not transplant six-year limitation or the template’s particular notice/end terms to road injury claims. Claims against an entity not party to a standstill require separate scrutiny; the judgment did not finally settle disputed party identity. No damages awarded in this interlocutory judgment. Some judgment date arithmetic appears erroneous: [54] says less than a month from 28 April to 22 June; [74] states 9 November 2015 for one cause where earlier analysis states 2009. Neither passage is used for a calculation here.
Status and authority
PROCEDURAL STAGE
Interlocutory contractual limitation ruling
APPEAL STATUS · NOT CONFIRMED
The order in this judgment is established; later appeal history not confirmed by the recorded official searches.
LATER TREATMENT
No appeal or contrary appellate determination of this interpretation was identified by the bounded official searches recorded in research_notes.
BINDING EFFECT
First-instance English High Court decision. Persuasive, subject to superior authority; not a universal rule for every injury standstill or for Scotland and Northern Ireland.
Guides that use this decision
The judgment
This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.
Sources
The numbers match the sources of the guide this summary was researched for.
[59] Russell & Anor v Stone (t/a PSP Consultants) & Ors · [1]; [5]; [37]; [46]; [56]
In these proceedings, which were commenced on 1 December 2016, the claimants seek almost £2.2 million in damages against the defendants arising out of the defendants’ quantity surveying and project management services in respect of extensive building works carried out at the claimants’ property at 36 Millfield Lane, Highgate, in North London.
Many of them concern the proper construction of three ‘Standstill Agreements’ entered into between the parties on 5 November 2015, 18 February 2016 and 28 April 2016 respectively.
But Ms McCafferty is quite right to say that those findings merely reflect the wording of the particular agreement in those cases, and do not set out any wider principle.
Everything points to the Standstill Agreements operating to suspend time (i.e. preserving both sides’ positions so that, at the end of the agreement, they are both in the same position in relation to limitation as they were when they entered into the agreement).
For all those reasons, therefore, I conclude that the Standstill Agreements operated to suspend time and not to extend time. As a result of that, when the third Standstill Agreement came to an end, in respect of the three claims where I have found that the cause of action accrued on 22 June 2010, the claimants had (by reference to that agreement alone) a period of over three weeks remaining to them in which to commence these proceedings. They did so. Those three claims are not therefore statute-barred.
Accordingly, in a rather longwinded way, the parties extended the period set out in the third and final Standstill Agreement to 30 November 2016. It is the defendants’ case that the claimants had to commence proceedings by that date, and they argue that, because the proceedings were not issued until the following day (1 December 2016), the claimants cannot avail themselves of the Standstill Agreements and the three claims are statute-barred.
The principal argument between the parties was whether, on the true construction of the Standstill Agreements, they operated to suspend time for the purposes of limitation, or to extend time for those purposes. In other words, on the claimants’ case, if they had a period of, say, one month remaining out of the six years when they entered into the Standstill Agreements, they still had a period of one month when the third Standstill Agreement came to an end. On the defendants’ case, because they say that the Standstill Agreements operated to extend time rather than to suspend it, they submit that the time for commencing proceedings finished when the third Standstill Agreement came to an end, on 30 November 2016. Thus they argue that the claim form was one day late.
(b) If I am wrong about that, however, then there is an irreconcilable inconsistency between Recital B and clause 2: the former talks about extending time, the latter about suspending time. In those circumstances, the authorities noted in paragraphs 34-35 above make clear that such an inconsistency must be decided in favour of clause 2. Clause 2 contains the operative provisions of the agreement and must always take precedence over the Recital.
In my view, that cause of action is not statute-barred. It would be wrong to construe the third Standstill Agreement in isolation, without regard to the first and second Standstill Agreements. The period covered by the first two Standstill Agreements was continuous, running from 5 November 2015 to 29 April 2016, and the court should construe the third Standstill Agreement as coming into effect on 28 April 2016, when time was still suspended. Any other conclusion would fail to treat the three Standstill Agreements together.
It seems to me overwhelmingly likely that the second defendant will play no part in this trial. Although the court cannot reach a final view as to the role played by the second defendant until after disclosure, I would be hopeful that the matter could be resolved between the solicitors long before that. But, given the lateness with which the point was taken, I do not consider that it would be appropriate to strike out all of the claims against the second defendant at this stage.
As a matter of strict logic, it did seem to me that the three claims (i), (ii) and (iii) cannot now be made against the second defendant. On the face of it, the second defendant was not a party to the Standstill Agreements. For the reasons explained above, the claimants are only able to bring the three claims against the first/third defendant because of the operation of the Standstill Agreements. Thus it would seem to follow that, because the second defendant was not a party to those Standstill Agreements, the claimants cannot avail itself of the same benefits.
However, whilst Ms Jones accepted that, she pointed out that the entity “PSP Consultants”, referred to in the Standstill Agreements might still be a reference to the limited company. That seems to me unlikely. However I am prepared to give the claimants the benefit of the doubt for a little longer in order to bottom out this point. As noted above, I would be confident that in the fairly near future, the second defendants will be deleted from these proceedings.
For the reasons set out in Section 6 above, the claimants were not obliged to act in breach of the third Standstill Agreement and issue proceedings against the defendants on 30 November 2016. Further, the Standstill Agreements operated to suspend time. Since the claimants were not out of time in respect of any causes of action in relation to the three claims before entering into the Standstill Agreements, and they issued the proceedings the day after the end of the third Standstill Agreement, the claims are not statute-barred.
About this sourceOfficial text
General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.