Peter Brooks v Zurich Insurance Public Limited Company & Anor

CITATION
[2022] EWHC 1170 (QB)
COURT
High Court of Justice, Queen’s Bench Division
LEGAL SYSTEM
England and Wales
DATE OF DECISION
20 May 2022
APPEAL STATUS
Not confirmed
PARAGRAPHS RELIED ON
Peter Brooks v Zurich Insurance Public Limited Company & Anor: [1]–[7], [18]–[21], Redman v Zurich Insurance Plc & Anor (Rev 1): [8]–[13], [23]–[29]

THE LEGAL QUESTION

Was the claim necessarily governed by the saved older regime?

The facts

The employers had dissolved before the Act commenced, but it was disputed when the worker’s actionable loss arose. [174]

What the court decided

Both the insurers’ strike-out request and the claimant’s cross-application were refused. [174]

Why: the reasoning

The completion of the cause of action turned on facts that should be found before deciding the governing regime. [174]

Why it matters and its limits

Later application of the transitional test, rather than an appeal from Redman.

WHAT IT DOES NOT DECIDE

  • No substantive ruling on medical causation or policy payment.

Status and authority

PROCEDURAL STAGE

Strike-out application and oral cross-application.

APPEAL STATUS · NOT CONFIRMED

No further disposition relied on or established by name/citation searches.

LATER TREATMENT

The court followed Redman as to when liability is incurred. [173]

BINDING EFFECT

First-instance decision; the procedural ruling did not decide the date of accrual.

Guides that use this decision

What can I do if my accident judgment or settlement isn’t paid?Guide · Main guide

The judgment

This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.

Sources

The numbers match the sources of the guide this summary was researched for.

  1. [173] Redman v Zurich Insurance Plc & Anor (Rev 1) · [8]–[13], [23]–[29]

    Soon after, ESJS1 was the subject of a voluntary winding up on 30 January 2014 and was eventually dissolved on 30 June 2016.
    Liability is incurred when the cause of action is complete and not when the claimant’s rights against the wrongdoer are thereafter crystallised whether by judgment or otherwise.
    His brave submission was that the proper interpretation of the transitional provisions is that the application of the 1930 Act does not preclude the retrospective but parallel operation of the 2010 Act to all claims which hitherto had fallen exclusively within the scope of the older legislation.
    It follows that the application to strike out the claim under the 2010 Act must succeed under CPR 3.4 on the basis that it discloses no reasonable grounds for bringing a claim.
    About this sourceOfficial text
  2. [174] Peter Brooks v Zurich Insurance Public Limited Company & Anor · [1]–[7], [18]–[21]

    For present purposes, “relevant person” includes a dissolved company. The Ruberoid companies were dissolved long before the Act came into force. So the question is when liability to the claimant was incurred. Turner J in the Redman case held that a relevant person incurs a liability under section 1 of the 2010 Act when the cause of action is complete and not when the claimant has established the right to compensation against the wrongdoer whether by a judgment or otherwise. Was the claimant’s cause of action against his employers complete before 1 August 2016?
    For these reasons I refuse the defendants’ application.
    It follows that I should also refuse the cross-application – made orally at the hearing – that I should enter judgment in the claimant’s favour on this issue. I will, rather, give directions leading to a speedy trial.
    About this sourceOfficial text

General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.

Install on iPhone or iPad

  1. Tap the Share button in Safari (the square with an upward arrow).
  2. Choose Add to Home Screen.
  3. Tap Add. The app appears next to your other apps.

The first steps after a collision, the checklists and the glossary stay available without signal.