THE LEGAL QUESTION
Was the explained tender delay unreasonable, and was counsel justified?
The facts
An employment-injury claim was sisted for investigation. A medical report was delayed by appointments; the tender was accepted after it arrived.
What the court decided
Delay was lengthy but reasonable; pursuer’s expenses and counsel sanction granted. A procedural dispensing power was exercised for the defender’s application.
Why: the reasoning
Stage, duration and explanation matter. Independent medical evidence was necessary on these facts; written QOCS motions remain the expected procedure.
Why it matters and its limits
A factual comparator on justified delay and proper applications.
WHAT IT DOES NOT DECIDE
First instance; five months is not a safe period.
Status and authority
PROCEDURAL STAGE
Expenses and counsel-sanction motions following tender acceptance.
APPEAL STATUS · NOT CONFIRMED
The disposition in this opinion is verified. No published further appeal found in the recorded searches; absence of a lodged appeal cannot be certified.
LATER TREATMENT
Considered and distinguished in Gasper [2025] CSOH 96 [6], [10]. No published appeal identified to 1 November 2026.
BINDING EFFECT
Scottish first-instance decision; persuasive in comparable cases, subject to appellate authority. It does not bind courts in the other UK legal systems.
Guides that use this decision
The judgment
This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.
Sources
The numbers match the sources of the guide this summary was researched for.
[45] Peter Gasper v The Partners of Tain & Fearn Medical Practice and National Health Service Education for Scotland · [1]–[18], particularly [9]–[18]; additional pinpoints [1], [11], [14], [15], [18]
There was undoubtedly delay: whether it was unreasonable or not must be judged objectively.
The pursuer sued the defenders for damages of £2 million
Following that approach the defenders lodged a joint tender in the sum of £30,000 (net of any liability that the defenders may have in terms of section 6 of the Social Security (Recovery of Benefits) Act 1997, together with the expenses of process to the date of the tender, on 11 December 2024.
Dealing with the relevant factors in turn, the delay of more than 8 months is a lengthy one which calls for explanation.
I find that there was an unreasonable delay on the part of the pursuer in accepting the tender.
while he is entitled to expenses to the date of the tender, the defenders are entitled to expenses from that date.
There is nothing in the language of the rule to suggest that the court has any discretion, or power, to vary the 75% to some other percentage.
I will also grant the defenders’ motion for expenses from the date of the tender, ordering in terms of RCS 41B.3(2)(c) that the pursuer’s liability is not to exceed an aggregate sum, paid to both defenders, of 75% of the amount of damages awarded to the pursuer, that sum to be calculated in the manner specified in RCS 41B.3(2)(c).
About this sourceOfficial text[46] Jamie Anderson v Emtelle UK Limited · [1]–[20], particularly [3]–[4], [12]–[14], [18]; additional pinpoints [13], [19]
Taking all those circumstances into account, I consider that while the delay was lengthy, it was not unreasonable.
just over five months passed between the date the tender was lodged, and the date of acceptance.
I will grant the pursuer’s motion 7/3, including sanction for junior counsel.
About this sourceOfficial text
General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.