The Members of the Probitas Syndicate 1942 at Lloyd’s for the 2022 Underwriting Year of Account v Pro 2 Care Limited
PUBLISHED BY · The National Archives, Find Case LawNATIONS · UK-wideCHECKED · 3 November 2026
This judgment is cited in one guide on this site. Below you will find the official text, the version we read, the guides that cite it and the exact passages they quote.
OUR SUMMARY · COURT DECISION
The Members of the Probitas Syndicate 1942 at Lloyd’s for the 2022 Underwriting Year of Account v Pro 2 Care Limited
[2025] EWHC 1921 (Comm) · High Court of Justice, King’s Bench Division, London Circuit Commercial Court · 25 July 2025
What did the court decide about unreasonable insurer delay and what was outside its decision?
OFFICIAL TEXT · PRIMARY SOURCE
Read the official version
The full judgment is published at the source below. Our pages explain it in general terms and do not replace it.
VERSION AND DATES
The version the guides were researched from.
| Version | Status | Source |
|---|---|---|
| 25 July 2025[2025] EWHC 1921 (Comm) | —PUBLISHED 25 JULY 2025 | caselaw.nationalarchives.gov.uk |
GUIDES THAT CITE IT
QUOTED PASSAGES
Passages quoted in the guides 9 PASSAGES
The exact words the guides rely on, with where each passage sits in the document and the version it comes from.
[49] · version of 25 July 2025
On 21 December 2022, water pipes burst inside the Property, which caused damage to the Property and disrupted the progress of the renovation works. Pro 2 Care sought Property Damage cover from Probitas under the terms of the Policy.
[52] · version of 25 July 2025
In July 2024, Pro 2 Care accepted an additional sum of £381,221.68 in satisfaction of any claim under the Policy for Property Damage.
[189] · version of 25 July 2025
Pro 2 Care says it took about 19 months for Probitas to pay the Property Damage claim. The vast bulk of the claim was not paid until 30 July 2024. That was unreasonable in respect of about 11 months: Defence para. 36. Had the claim been paid sooner, repair works would have started sooner and finished sooner. Revenue would have been earned sooner from the Property.
[190] · version of 25 July 2025
By way of example, in Quadra Commodities SA v XL Insurance Co SE [2022] EWHC 431 at [140-143], Butcher J held on the facts before him that one year was the reasonable time for investigating, evaluating and paying the complex international and uncertain claim arising from a large scale fraud.
[194] · version of 25 July 2025
The issue of unreasonable delay under section 13A is a paradigm example of a factual dispute which requires evidence and cannot be resolved summarily.
[194] · version of 25 July 2025
The issue of unreasonable delay under section 13A is a paradigm example of a factual dispute which requires evidence and cannot be resolved summarily. I cannot be satisfied that I have before me all the evidence necessary for the proper determination of the counterclaim. This is the case both as to period of delay and loss.
[195] · version of 25 July 2025
I do not think it necessary to reach a concluded view on this point, but consider Pro 2 Care’s approach to be clearly arguable. It would be better decided at trial in the light of the evidence as a whole. I shall therefore decline summary judgment on this point.
[195] · version of 25 July 2025
I do not think it necessary to reach a concluded view on this point, but consider Pro 2 Care’s approach to be clearly arguable.
[197] · version of 25 July 2025
I shall grant summary judgment in favour of Probitas in relation to its claim for the declaration sought. I shall dismiss Pro 2 Care’s counterclaim for a declaration to contrary effect. The section 13A counterclaim will go forward to trial.