Robert Taylor v Peter Jones & Anor
PUBLISHED BY · Court of Appeal (Civil Division)NATIONS · England and WalesCHECKED · 6 November 2026
This judgment is cited in one guide on this site. Below you will find the official text, the version we read, the guides that cite it and the exact passages they quote.
OUR SUMMARY · COURT DECISION
Taylor v Jones and another; Taylor v Spriggs
[2024] EWCA Civ 170 · Court of Appeal (Civil Division) · 28 February 2024
Were costs to remedy a pre-existing defect recoverable as compensation for works under the Act, and was the County Court wrong to regard the adjoining owners as the successful parties on costs?
OFFICIAL TEXT · PRIMARY SOURCE
Read the official version
The full judgment is published at the source below. Our pages explain it in general terms and do not replace it.
VERSION AND DATES
The version the guides were researched from.
| Version | Status | Source |
|---|---|---|
| 28 February 2024Judgment handed down 28 February 2024 | —PUBLISHED 28 FEBRUARY 2024 | caselaw.nationalarchives.gov.uk |
GUIDES THAT CITE IT
QUOTED PASSAGES
Passages quoted in the guides 15 PASSAGES
The exact words the guides rely on, with where each passage sits in the document and the version it comes from.
[1] · version of 28 February 2024
These appeals from the County Court concern awards under the Party Wall etc. Act 1996 (“the Act”). The Appellant, Mr Robert Taylor, carried out work in the garden of his property. In the language of the Act he was the “building owner” and as such liable to compensate any “adjoining owner” for any damage which might result to them by reason of any work executed in pursuance of the Act. The Respondents, Mr and Mrs Jones and Mr Spriggs, are respectively the owners of two mews properties which lie to the rear of Mr Taylor’s garden and which were affected by his works and are adjoining owners for the purposes of the Act.
[27] · version of 28 February 2024
In summary therefore the essential facts are that Mr Taylor’s works caused the rear wall of Nos 5 and 6 to drop by a very modest amount (2mm), but this in turn caused the internal walls and floor slabs to drop by a more significant amount (40mm). His works did not cause the long-standing problems that the rear wall is unsupported by its foundations and operates as an arch over the dpc crack, or that there are extensive voids beneath the floor slabs and the internal walls.
[38], table · version of 28 February 2024
The overall result was as follows: Respondent Original Award Sought by Rs Judge’s award Mr and Mrs Jones 189,727.12 263,844.07 147,540.01 (with VAT) 215,316.28 166,374.19 Mr Spriggs 142,105.62 186,596.29 115,361.88 (with VAT) 165,873.54 135,085.80 She therefore made an order in each appeal dated 7 March 2023 substituting the figures in bold above for the higher figures in the awards.
[47] · version of 28 February 2024
In those circumstances I am inclined to agree with Mr Williamson, although I do not think we need to decide the point finally in the present appeal.
[51] · version of 28 February 2024
There is nothing unreasonable in Mr and Mrs Jones and Mr Spriggs wishing to repair their properties. There is no suggestion that they were about to demolish them, or wished to do anything other than go back to letting them as they had previously done, and the evidence was that repairs needed to be done before they could be re-let. So the answer to that question in the present case is also clear: they are to be compensated by awarding them the cost of repairing the damage caused by the works.
[57] · version of 28 February 2024
As Mr Isaac pointed out, and as the Judge accepted, Harbutt’s was not a case of remedying pre-existing damage. But it does establish the principle that if the owner of destroyed property (reasonably) rebuilds it, he does not have to give credit for the fact that he gets a new property instead of an old one. The same must apply where the owner of damaged property (reasonably) repairs the damage. Any repair will involve replacing old materials with new, but, as Cross LJ said, in practice you cannot do anything else and the defendant is not entitled to an allowance for that.
[58] · version of 28 February 2024
Harbutt’s was referred to by Lord Hope in Lagden. In that case the claimant’s car was damaged by the defendant’s negligence. He hired a replacement car, but was unable because of his financial circumstances to afford to pay spot hire rates and so took out a more expensive credit hire agreement. The question was whether he could recover the greater cost of doing so. That is some way removed from the present case, and raised rather different issues, and the House of Lords only decided that he could by a majority of 3 to 2.
[61] · version of 28 February 2024
In effect therefore Leggatt LJ identified three classes of case: (i) where the insured chooses to carry out improvements not needed for reinstatement; (ii) where the insured does not have a choice but derives a money benefit from an improvement; and (iii) where the insured does not have a choice but derives a non-money benefit from an improvement.
[63] · version of 28 February 2024
Second, the burden of proving that damages should be reduced on the basis that the insured will save money as a result of reinstatement lies on the insurer [98].
[70] · version of 28 February 2024
I think that was an understandable conclusion in the light of the argument she appears to have received. But to my mind there is, as I have suggested above, a further question that needs to be asked. It is not enough to ask whether it is necessary to do any particular work when carrying out the repairs. I think it is also necessary to ask whether the work that now needs to be done has to be done in order to repair the relevant damage, that is the damage caused by Mr Taylor’s works.
[72] · version of 28 February 2024
Mr Taylor’s works therefore caused damage to each of the three eastern slabs. He is therefore liable for the cost of repairing or replacing them. The floor slabs are intended to rest on solid ground not over a void. So to repair or replace them it is necessary to fill in the voids. The cost of filling in these voids therefore has to be borne by Mr Taylor as it is necessary to fill them in as it is the only practical way in which the floor slabs can be re-laid, and hence it is needed in order to repair the damage to the slabs which his works caused.
[78] · version of 28 February 2024
In my judgement it follows that Mr Taylor is not liable for the cost of underpinning the rear wall of Nos 5 and 6 any more than he would be liable for the cost of filling the void under the floor slab in the lounge of No 6. The underpinning is needed, but it is not needed to remedy the damage caused by his works. It is, as Mr Isaac submitted, needed to remedy pre-existing defects which his works did not cause. There is therefore no reason why he should be required to compensate Mr and Mrs Jones and Mr Spriggs for the cost of the underpinning as he would not thereby be compensating them for damage caused by the work he carried out. The reality is that they had a defective building long before Mr Taylor carried out his works; his works have brought the defect to light which has made it necessary for them to do something about it, but the defect was not caused by him or his works, and I do not think the Act requires him to pay for remedying it.
[80] · version of 28 February 2024
It follows that the case will have to be remitted to the County Court for a finding as to how much of the cost of the works allowed by the Judge was attributable to work which Mr Taylor is not liable for. In that case however I would very much hope that the parties would be able to agree the figures to avoid the necessity of any further hearing.
[99] · version of 28 February 2024
I would allow the appeal on Ground 2.
[100] · version of 28 February 2024
It follows that the costs of the hearing below will have to be revisited, and on this I would invite brief written submissions (if not agreed), but I would not accept the criticisms of the Judge advanced in Ground 1.