Conarken Group Ltd and Farrell Transport Ltd v Network Rail Infrastructure Ltd

CITATION
[2011] EWCA Civ 644
COURT
Court of Appeal (Civil Division)
LEGAL SYSTEM
England and Wales
DATE OF DECISION
27 May 2011
APPEAL STATUS
Final
PARAGRAPHS RELIED ON
[2]–[3], [69], [101], [104], [156], TCC [77](a)–(b), Supreme Court results, PDF p. 1, Armstead [33], [36]

THE LEGAL QUESTION

Can Network Rail recover payments to train operators for temporary loss of use of the damaged railway under its track access contracts?

The facts

In July 2002 a lorry damaged a railway bridge parapet at Howden. In May 2003 a vehicle detached overhead equipment at Bathley Lane near Newark. The two closures prevented operation of the affected lines. The defendants admitted liability for physical repair. The parties agreed the quantum on the relevant contractual calculation, but disputed recoverability of the additional sums.

What the court decided

The court dismissed the appeal. The Schedule 8 sums were recoverable in the circumstances.

Why: the reasoning

Pill LJ treated the agreement and the reasonable estimate as relevant without allowing contracting parties to dictate an outsider’s liability. Moore-Bick LJ regarded the payments as net loss of revenue flowing from physical damage, within the foreseeable kind of loss, subject to remoteness. Jackson LJ agreed with the result; the defendants accepted that the calculation was a reasonable assessment of the operators’ losses.

Why it matters and its limits

Shows why a road authority or asset owner needs evidence linking any separate claimed loss to physical damage; agreement on a contractor rate does not itself settle liability.

WHAT IT DOES NOT DECIDE

  • The cases involved rail revenue and admitted physical repair liability; they do not set a road barrier rate or decide proof of disputed vehicle identity.

  • The Schedule 8 figures were accepted as a reasonable estimate. The three judges’ reasoning is not treated as identical.

Status and authority

PROCEDURAL STAGE

Appeal from Akenhead J, Technology and Construction Court, [2010] EWHC 1852 (TCC)

APPEAL STATUS · FINAL

UKSC 2011/0139: permission refused on 1 November 2011. This was not a Supreme Court ruling on the merits.

LATER TREATMENT

Armstead [33]–[36] discusses all three judgments and explains the case as allowing a reasonable contractual estimate of third-party revenue loss consequent on physical damage to revenue-generating property.

BINDING EFFECT

Court of Appeal authority binding on lower courts in England and Wales on its point of law, subject to the Supreme Court’s subsequent explanation. Persuasive in other legal systems where compatible.

Guides that use this decision

I’ve been sent a bill for damage to a crash barrier or road sign. What should I do?Guide · Main guideWhat happens after a collision with a tram or train or at a level crossing?Guide

The judgment

This summary explains the decision in general terms and does not replace the judgment. The full text is published at the official source; the passages the guides quote are on the judgment's page.

Sources

The numbers match the sources of the guide this summary was researched for.

  1. [58] Armstead v Royal & Sun Alliance Insurance Company Ltd · [33], [36]

    The Court of Appeal held that it could. Notably, it was conceded by the defendants that the sums calculated in accordance with Schedule 8 represented a reasonable estimate of the financial losses caused to the TOCs by the temporary unavailability of the track: see paras 11, 98 and 155 of the judgments. Each member of the court gave separate reasons for the decision and there were differences of approach, or at least of emphasis, between them. Pill LJ stressed that a finding or concession that the sums payable under the contracts between Network Rail and the TOCs were reasonable as between the contracting parties did not automatically mean that they were recoverable from the defendants.
    The Network Rail case is thus authority for the following proposition. Where physical damage is negligently caused to revenue-generating property, the loss recoverable by the owner of the property from the person who caused the damage includes a sum payable by the owner, under an agreement with another party to compensate that party for its loss of revenue resulting from the damage, provided the sum agreed is a reasonable estimate of the likely amount of that loss.
    About this sourceOfficial text
  2. [61] Conarken Group Ltd & Anor v Network Rail Infrastructure Ltd (Rev 1) · [2]–[3], [69], [101], [104], [156]

    In the first named case, the award was in the sum of £293,732.32 plus interest, and in the second £1,017,144.66 plus interest. In each case, physical damage had been caused to railway property owned by the respondents and caused by the negligent driving on the highway of drivers employed by the appellants. Liability for the cost of repairing the property was admitted; the issue was as to the extent of the appellants’ liability for other losses claimed.
    In July 2002, the negligence of Conarken’s driver at Howden, Yorkshire caused damage to the parapet walls of a railway bridge and rubble was strewn on the railway tracks. The line was closed for five days while repairs were carried out. On 10 May 2003, the negligence of Farrell’s driver at Bathley Lane, Newark, resulted in the detachment of overhead electric cables which affected the use of the East Coast Main Line (“ECML”) for about seven hours.
    It is not open to a party to dictate to the whole world the extent of tortious liability and what is reasonably foreseeable and not too remote in order to achieve what it regards as a satisfactory contract with a third party.
    I think it is clear, therefore, that two types of loss flow naturally from any damage to the infrastructure that renders the track itself unavailable for use: the cost of repair and the loss of revenue attributable to the loss of availability of the track itself. Both are in my view within the scope of the duty of the motorist, or indeed anyone else, to exercise reasonable care not to cause physical damage to the infrastructure. Subject to the limitations imposed by the rules relating to remoteness, therefore, all such loss is in principle recoverable from the person who caused the damage.
    For the reasons I have given I do not think that it is relevant to enquire into the precise nature of the loss incurred by the TOCs as a result of the disruption to services caused by these incidents, provided (as is accepted to be the case) that the compensation to be paid in respect of it represents a genuine estimate of its amount.
    In the result, therefore, I agree with the conclusion of Pill and Moore-Bick LJJ that this appeal must be dismissed.
    About this sourceOfficial text
  3. [62] Network Rail Infrastructure Ltd v Conarken Group Ltd · [77](a)–(b)

    as against Conarken, in the total sum of £293,742.32 made up of £127,070.62 and £166,661.70 in relation to the Schedule 8 losses and remedial works costs respectively.
    as against Farrell Transport, in the sum of £1,017,144.66 in relation to the Schedule 8 losses. There need be no judgement in relation to the cost of remedial works, the agreed sum for which was paid by Farrell Transport in mid-June 2010.
    About this sourceOfficial text
  4. [63] Permission to Appeal Results - November 2011 · PDF p. 1, UKSC 2011/0139 row

    Conarken Group Limited and another (Appellants) v Network Rail Infrastructure Limited (Respondent)
    UKSC 2011/0139
    Refused 1 November 2011
    About this sourceOfficial text

General information, not legal advice. Whether a decision applies to you depends on your facts and where you are in the UK.

Install on iPhone or iPad

  1. Tap the Share button in Safari (the square with an upward arrow).
  2. Choose Add to Home Screen.
  3. Tap Add. The app appears next to your other apps.

The first steps after a collision, the checklists and the glossary stay available without signal.